Model 5 Split & Fraction of work Practice Questions Answers Test with Solutions & More Shortcuts
time & work PRACTICE TEST [7 - EXERCISES]
Model 1 Basics on Time & Work
Model 2 Formula method ‘M1D1W1 = M2D2W2’
Model 3 Man leaves & joins
Model 4 Working with Man, Woman, Child
Model 5 Split & Fraction of work
Model 6 Efficiency of the worker
Model 7 Working with individual wages
Question : 36 [SSC CHSL 2015]
A can do in one day three times the work done by B in one day. They together finish $2/5$ of the work in 9 days. The number of days by which B can do the work alone is :
a) 120 days
b) 90 days
c) 30 days
d) 100 days
Answer »Answer: (b)
Let time taken by A alone in doing work be x days.
Time taken by B alone = 3x days
A and B together finish $2/5$ work in 9 days.
TIme taken by A and B in doing whole work
= ${9 × 5}/2 = 45/2$ days
$1/x + 1/{3x} = 2/45$
${3 + 1}/{3x} = 2/45$
$4/{3x} = 2/45$ ⇒ 2 × 3x = 4 × 45
$x = {4 × 45}/{2 × 3}$ = 30 days
Time taken by B = 3x days = 3 × 30 = 90 days
Using Rule 22The efficiency of A to work is 'n' times more than that of B, Both start to work together and finish it in 'D' days. Then, A and B will separately complete, the work in $({n + 1}/n)$D and (n + 1)D days respectively.
Here, n = 3 and D = ${9 × 5}/2 = 45/2$ days
(Time taken to finish whole work)
Time taken by B = (n + 1)D
= (3 + 1) × $45/2$ = 90 days
Question : 37 [SSC CGL Prelim 2000]
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days, then the fraction of the work that is left is:
a) $7/15$
b) $8/15$
c) $1/10$
d) $1/4$
Answer »Answer: (b)
Using Rule 2If A completes a piece of work in 'x' days, and B completes the same work in 'y' days, then,Work done by A in 1 day = $1/x$, Work done by B in 1 day = $1/y$ Work done by A and B in 1 day = $1/x + 1/y = {x + y}/{xy}$Total time taken to complete the work by A and B both = $({xy}/{x + y})$
A’s work per day = $1/15$
B’s work per day = $1/20$
(A+ B)’s work per day
= $1/15 + 1/20 = {4 + 3}/60 = 7/60$
(A + B)’s work in 4 days
= $4 × 7/60 = 7/15$
Left work = $1 - 7/15 = {15 - 7}/15 = 8/15$
Question : 38 [SSC CGL Tier-II 2015]
A, B and C are employed to do a piece of work for Rs. 5,290. A and B together are supposed to do $19/23$ of the work and B and C together $8/23$ of the work. Then A should be paid
a) Rs.3,450
b) Rs.4,250
c) Rs.2,290
d) Rs.1,950
Answer »Answer: (a)
Part of work done by A and B = $19/23$
Part of work done by C = $1 - 19/23 = 4/23$
Part of work done by B and C = $8/23$
Part of work done by B
= $8/23 - 4/23 = 4/23$
Part of work done by A
= $19/23 - 4/23 = 15/23$
Ratio of the shares of wages of A, B and C
= $15/23 : 4/23 : 4/23$ = 15 : 4 : 4
A’s share = $15/23$ × 5290 = Rs.3450
Question : 39 [SSC CGL Tier-I 2016]
A can do $1/3$ rd of a work in 5 days and B can do $2/5$th of this work in 10 days. Both A and B, together can do the work in
a) 8$4/5$ days
b) 7$3/8$ days
c) 10 days
d) 9$3/8$ days
Answer »Answer: (d)
A does $1/3$ rd part of work in 5 days.
A will do 1 work in 5 × 3 = 15 days.
B does $2/5$ th of work in 10 days.
B will do 1 work in ${10 × 5}/2$ = 25 days.
(A + B)’s 1 day’s work
= $1/15 + 1/25 = {5 + 3}/75 = 8/75$
∴ Required time
= $75/8 = 9{3}/8$ days
Question : 40 [SSC CISF ASI 2010]
A can complete $2/3$ of a work in 4 days and B can complete $3/5$ of the work in 6 days. In how many days can both A and B together complete the work ?
a) 2
b) 3
c) 2$7/8$
d) 3$3/4$
Answer »Answer: (d)
Using basics of Rule 2,
Time taken by A to complete the work
= ${4 × 3}/2$ = 6 days
Time taken by B to complete the work
= ${6 × 5}/3$ = 10 days
(A + B)’s 1 day’s work
= $1/6 + 1/10 = {5 + 3}/30 = 8/30 = 4/15$
A and B together will complete the work in
$15/4 = 3{3}/4$ days.
IMPORTANT quantitative aptitude EXERCISES
-
Top 199+ Basic Time and Work Aptitude MCQs with Answers »
-
Top 200+ Time and Work Problem Solving By Formula Method »
-
New 189+ Time & Work MCQs Practice Test for BANK Exams »
-
Top 199+ Time & Work MCQs: Men Women Child for BANK Exam »
-
Top 199+ Time and Work Questions Test on Fraction of Work »
-
Top 199+ Time and Work Efficiency Based Aptitude MCQ Quiz »
-
New 299+ Time and Work Aptitude Test On Individual Wages »
Model 5 Split & Fraction of work Shortcuts »
Click to Read...Model 5 Split & Fraction of work Online Quiz
Click to Start..time & work Shortcuts and Techniques with Examples
-
Model 1 Basics on Time & Work
Defination & Shortcuts … -
Model 2 Formula method ‘M1D1W1 = M2D2W2’
Defination & Shortcuts … -
Model 3 Man leaves & joins
Defination & Shortcuts … -
Model 4 Working with Man, Woman, Child
Defination & Shortcuts … -
Model 5 Split & Fraction of work
Defination & Shortcuts … -
Model 6 Efficiency of the worker
Defination & Shortcuts … -
Model 7 Working with individual wages
Defination & Shortcuts …
quantitative aptitude CATEGORIES
RECENT BLOGS
Recently Added Subject & Categories For All Competitive Exams
SSC STENO: Speed Time and Distance MCQ Questions Test PDF
Free Time and Distance Aptitude-based Practice multiple questions with solutions, Quiz series, Mock Test & Download PDF for SSC Steno (Grade C & D) 2024 Exam
Continue Reading »
SSC STENO: Time & Work Questions Solved Problems with PDF
Free Time and work Aptitude-based Practice multiple questions with solutions, Quiz series, Mock Test & Downloadable PDF for SSC Steno (Grade C & D) 2024 Exam
Continue Reading »
SSC STENO 2024: Free Reading Comprehension MCQ Test PDF
Top Reading Comprehension English Section-wise multiple choice questions and answers, Full Mock Test Series & Online Quiz for SSC Steno Grade C & D 2024 Exam
Continue Reading »
Free Percentage Questions Answers for SSC STENO 2024 Exam
Important Top Percentage Aptitude-based multiple choice questions and answers practice quiz series, Online Mock Test PDF for SSC Steno Grade C & D 2024 Exam
Continue Reading »