Question : 16 [SSC CHSL 2010]
P can complete $1/4$ of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes $1/3$ of the work in 13 days and S, $1/6$ of the work in 7 days. Who will be able to complete the work first ?
a) Q
b) P
c) S
d) R
Answer »Answer: (a)
Time taken by P in completing 1 work
= 10 × 4 = 40 days
Time taken by Q in completing 1 work
= ${15 × 5}/2 = 75/2$ days
Time taken by R in completing 1 work
= 13 × 3 = 39 days
Time taken by S in completing 1 work
= 7 × 6 = 42 days
Clearly, Q took the least time i.e. $75/2$ or 37${1}/2$ days.
Question : 17 [SSC CGL Tier-1 2011]
A does half as much work as B in three- fourth of the time. If together they take 18 days to complete a work, how much time shall B take to do it alone?
a) 35 days
b) 30 days
c) 45 days
d) 40 days
Answer »Answer: (b)
Using Rule 2,
Let B completes the work in x days.
Work done by A in ${3x}/4$ days = $1/2$
Time taken by A in completing the work = $2 × {3x}/4 = {3x}/2$ days
(A + B)’s 1 day’s work
= $1/x + 2/{3x} = {3 + 2}/{3x} = 5/{3x}$
$5/{3x} = 1/18$ ⇒ 3x = 90 ⇒ x = 30
Hence, time taken by B in completing the work = 30 days
Question : 18 [SSC CGL Prelim 2007]
A contractor undertook to complete a project in 90 days and employed 60 men on it. After 60 days, he found that $3/4$ of the work has already been completed. How many men can he discharge so that the project may be completed exactly on time ?
a) 20
b) 40
c) 15
d) 30
Answer »Answer: (a)
Using Rule 1,
Days | Work | Men |
60 | $3/4$ | 60 |
↑ | ↓ | ↓ |
30 | $1/4$ | x |
∴ ${30 : 60}/{3/4 : 1/4}]$ : : 60 : x
$30 × 3/4 × x = 60 × 1/4 × 60$
$x = {60 × 60}/{30 × 3}$ = 40
Question : 19 [SSC CGL Tier-I 2016]
A, B and C contract a work for Rs. 440. A and B together are to do $9/11$ of the work. The share of C should be :
a) Rs. 90
b) Rs. 75
c) Rs. 80
d) Rs. 100
Answer »Answer: (c)
Work done by A and B together = $9/11$ parts
Work done by C = $1 - 9/11 = 2/11$ parts
Total amount = Rs. 440
∴ C’s share = Rs.$(2/11 × 440)$ = Rs.80
Question : 20 [SSC CGL Tier-I 2016]
A and B together can complete a work in 24 days. B alone does $1/3$ rd part of this work in 12 days. How many days will A alone take to complete the remaining work?
a) 36 days
b) 24 days
c) 72 days
d) 48 days
Answer »Answer: (d)
B completes $1/3$ work in 12 days.
B will complete 1 work in 12 × 3 = 36 days.
B’s 1 day’s work = $1/36$
(A + B)’s 1 day’s work = $1/24$
A’s 1 day’s work = $1/24 - 1/36$
= ${3 - 2}/72 = 1/72$
Time taken by A in doing 1work = 72 days
∴ Remaining work
= $1 - 1/3 = 2/3$
Time taken by A in doing $2/3$ work
= $2/3$ × 72 = 48 days
IMPORTANT quantitative aptitude EXERCISES
-
Top 199+ Basic Time and Work Aptitude MCQs with Answers »
-
Top 200+ Time and Work Problem Solving By Formula Method »
-
New 189+ Time & Work MCQs Practice Test for BANK Exams »
-
Top 199+ Time & Work MCQs: Men Women Child for BANK Exam »
-
Top 199+ Time and Work Questions Test on Fraction of Work »
-
Top 199+ Time and Work Efficiency Based Aptitude MCQ Quiz »
-
New 299+ Time and Work Aptitude Test On Individual Wages »
Model 5 Split & Fraction of work Shortcuts »
Click to Read...Model 5 Split & Fraction of work Online Quiz
Click to Start..time & work Shortcuts and Techniques with Examples
-
Model 1 Basics on Time & Work
Defination & Shortcuts … -
Model 2 Formula method ‘M1D1W1 = M2D2W2’
Defination & Shortcuts … -
Model 3 Man leaves & joins
Defination & Shortcuts … -
Model 4 Working with Man, Woman, Child
Defination & Shortcuts … -
Model 5 Split & Fraction of work
Defination & Shortcuts … -
Model 6 Efficiency of the worker
Defination & Shortcuts … -
Model 7 Working with individual wages
Defination & Shortcuts …
quantitative aptitude CATEGORIES
RECENT BLOGS
Recently Added Subject & Categories For All Competitive Exams
100+ Quadratic Equation Questions Answers PDF for Bank
Quadratic Equation multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams
Continue Reading »
IBPS Aptitude Linear Equations MCQ Questions Answers PDF
Linear equations multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams
Continue Reading »
New 100+ Compound Interest MCQ with Answers PDF for IBPS
Compound Interest verbal ability questions and answers solutions with PDF for IBPS RRB PO. Aptitude Objective MCQ Practice Exercises all competitive exams
Continue Reading »
100+ Mixture and Alligation MCQ Questions PDF for IBPS
Most importantly Mixture and Alligation multiple choice questions and answers with PDF for IBPS RRB PO. Aptitude MCQ Practice Exercises all Bank Exams
Continue Reading »