Question : 16 [SSC CGL Prelim 2004]

A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last ?

a) 20 days

b) 15 days

c) 6 days

d) 10 days

Answer: (d)

A’s 1 day’s work = $1/20$

A’s 4 days’ work = $4/20 = 1/5$

Remaining work = $1 - 1/5 = 4/5$

This part is completed by A and B together.

Now, (A + B)’s 1 day’s work = $1/20 + 1/12$

= ${3 + 5}/60 = 8/60 = 2/15$

Now, $2/15$ work is done by (A + B) in 1 day.

$4/5$ work is done in

= $15/2 × 4/5$ = 6 days.

Hence, the work lasted for 4 + 6 = 10 days.

Question : 17 [SSC CGL Prelim 2008]

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed?

a) 10 days

b) 9.6 days

c) 9 days

d) 12 days

Answer: (c)

Let the work be finished in x days.

According to the question,

A worked for x days while B worked for (x - 3) days

$x/18 + {x - 3}/12 = 1$

${2x + 3x - 9}/36 = 1$

5x - 9 = 36

5x = 45 ⇒ x = $45/5$ = 9

Hence, the work was completed in 9 days.

Using Rule 8
(i) If A can do a work in 'x' days and B can do the same work in 'y' days and when they started working together, B left the work 'm' days before completion then
total time taken to complete work is ${(y + m)x}/{x + y}$
(ii) A leaves the work 'm' days before its completion then total time taken to complete work is = ${(x + m)y}/{x + y}$

Here, x = 18, y = 12, m = 3

Total time taken = $({y + m}/{x + y})x$

= $({12 + 3}/{18 + 12})$ × 18 = 9 days

Question : 18 [SSC CGL Prelim 1999]

A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?

a) 10 days

b) 6 days

c) 8 days

d) 12 days

Answer: (c)

Work done by (A + C) in 2 days

= $2(1/10 + 1/20) = 2({2 + 1}/20) = 6/20 = 3/10$

Remaining work = $1 - 3/10 = 7/10$

(B + C)’s 1 day’s work

= $1/15 + 1/20 = {4 + 3}/60 = 7/60$

Time taken by (B + C) to finish $7/10$ part of the work

= $60/7 × 7/10$ = 6 days

Total time = 2 + 6 = 8 days

Question : 19 [SSC CGL Prelim 1999]

A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in :

a) 5$1/3$ days

b) 8 days

c) 10 days

d) 5 days

Answer: (a)

Since, A can finish the work in 18 days.

A’s one day’s' work = $1/18$

Similarly, B’s one day’s work = $1/24$

(A + B)’s 8 days’ work = $(1/18 + 1/24) × 8 = 7/72 × 8 = 7/9$

Remaining work = $1 - 7/9 = 2/9$

Time taken to finish the remaining work by B is $2/9 × 24 = 16/3 = 5{1}/3$ days

Using Rule 20
A can do a certain work in 'm' days and B can do the same work in 'n' days. They worked together for 'P' days and after this A left the work, then in how many days did B alone do the rest of work ?
Required time = ${mn - P(m + n)}/m$ days
when after 'P' days B left the work, then in how many days did A alone do the rest of work?
Required time = ${mn - P(m + n)}/n$ days

Here, m = 18, n= 24 and p = 8

Required Time = ${18 × 24 - 8(18 + 24)}/18$

= ${432 - 336}/18 = 96/18$

= $16/3 = 5{1}/3$ days

Question : 20 [SSC CHSL 2010]

X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?

a) 14 days

b) 15 days

c) 16$2/3$ days

d) 13$1/3$ days

Answer: (d)

Part of the work done by X in 8 days.

=$8/40 = 1/5$

[Since, work done in 1 day = $1/40$]

Remaining work = $1 - 1/5 = 4/5$

This part of work is done by Y in 16 days.

Time taken by Y in doing 1 work

= ${16 × 5}/4$ = 20 days

Work done by X and Y in 1 day

= $1/40 + 1/20 = {1+2}/40 = 3/40$

Hence, both together will complete the work in $40/3$

i.e.$13{1}/3$ days.

IMPORTANT quantitative aptitude EXERCISES

Model 3 Man leaves & joins Shortcuts »

Click to Read...

Model 3 Man leaves & joins Online Quiz

Click to Start..

Recently Added Subject & Categories For All Competitive Exams

New 150+ Percentage Questions For IBPS Clerk Prelims 2024

Free Top Percentage Quants Aptitude based Multiple Choice Questions and Answers Practice Test Series, Quiz PDF & Mock Test for IBPS Clerk Prelims 2024 Exam

04-May-2024 by Careericons

Continue Reading »

Classification Reasoning MCQ For IBPS Clerk Prelims 2024

Most Important 100+ Classification based Verbal Reasoning Ability Multiple choice questions and answers PDF, Free New Mock tests For IBPS Clerk Prelims 2024

03-May-2024 by Careericons

Continue Reading »

Ratio and Proportion Questions with Solutions, IBPS Clerk

New Ratio and Proportion Quants Aptitude based Multiple Choice Questions and Answers Practice Test Series, Quiz & Mock Test for IBPS Clerk Prelims 2024 Exam

02-May-2024 by Careericons

Continue Reading »

Top Analogy Reasoning Ability For IBPS Clerk Prelims 2024

Most Important Analogy based Verbal Reasoning Multiple choice questions and answers practice quiz series PDF, Free New Mock tests For IBPS Clerk Prelims 2024

01-May-2024 by Careericons

Continue Reading »