Model 3 Man leaves & joins Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in :

(a) 5$1/3$ days

(b) 8 days

(c) 10 days

(d) 5 days

The correct answers to the above question in:

Answer: (a)

Since, A can finish the work in 18 days.

A’s one day’s' work = $1/18$

Similarly, B’s one day’s work = $1/24$

(A + B)’s 8 days’ work = $(1/18 + 1/24) × 8 = 7/72 × 8 = 7/9$

Remaining work = $1 - 7/9 = 2/9$

Time taken to finish the remaining work by B is $2/9 × 24 = 16/3 = 5{1}/3$ days

Using Rule 20
A can do a certain work in 'm' days and B can do the same work in 'n' days. They worked together for 'P' days and after this A left the work, then in how many days did B alone do the rest of work ?
Required time = ${mn - P(m + n)}/m$ days
when after 'P' days B left the work, then in how many days did A alone do the rest of work?
Required time = ${mn - P(m + n)}/n$ days

Here, m = 18, n= 24 and p = 8

Required Time = ${18 × 24 - 8(18 + 24)}/18$

= ${432 - 336}/18 = 96/18$

= $16/3 = 5{1}/3$ days

Practice time & work (Model 3 Man leaves & joins) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more man leaves and joins Based Quantitative Aptitude Questions and Answers

Question : 1

X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?

a) 14 days

b) 15 days

c) 16$2/3$ days

d) 13$1/3$ days

Answer: (d)

Part of the work done by X in 8 days.

=$8/40 = 1/5$

[Since, work done in 1 day = $1/40$]

Remaining work = $1 - 1/5 = 4/5$

This part of work is done by Y in 16 days.

Time taken by Y in doing 1 work

= ${16 × 5}/4$ = 20 days

Work done by X and Y in 1 day

= $1/40 + 1/20 = {1+2}/40 = 3/40$

Hence, both together will complete the work in $40/3$

i.e.$13{1}/3$ days.

Question : 2

8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

a) 3

b) 4

c) 5

d) 2

Answer: (b)

Using Rule 1
If $M_1$ men can finish $W_1$ work in $D_1$ days and $M_2$ men can finish $W_2$ work in $D_2$ days then, Relation is
${M_1D_1}/{W_1} = {M_2D_2}/{W_2}$ and
If $M_1$ men finish $W_1$ work in $D_1$ days, working $T_1$ time each day and $M_2$ men finish $W_2$ work in $D_2$ days, working $T_2$ time each day, then
${M_1D_1T_1}/{W_1} = {M_2D_2T_2}/{W_2}$

Work done by 8 men in 6 days

= $6/12 = 1/2$

Remaining work

= $1 - 1/2 = 1/2$

4 more men are engaged.

Total number of men = 8 + 4 = 12

By work and time formula

$W_1/{M_1D_1} = W_2/{M_2D_2}$, we have

$1/{8 × 12} = {1/2}/{12 × D_2}$

$D_2 = 1/2 × {8 × 12}/12$ = 4 days.

Question : 3

40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in

a) 53$1/3$ days

b) 52 days

c) 50 days

d) 56 $2/3$ days

Answer: (d)

For the first 10 days 40 men worked.

Now, 40 men can complete the work in 40 days

1 man will complete the same work in 1600 days

1 man’s 1 day’s work = $1/1600$

Part of work done in first 10 days = $1/4$

For the next 10 days 35 men worked.

Part of the work done

= ${1 × 35 × 10}/1600 = 7/32$

For the next 10 days, 30 men worked

Part of the work done

= ${30 × 10}/1600 = 3/16$

For the next 10 days, 25 men worked. Part of the workdone

= ${25 × 10}/1600 = 5/32$

Similarly, part of the work done by 20 men in next 10 days

= ${20 × 10}/1600 = 1/8$

Work done in 50 days

= $1/4 + 7/32 + 3/16 + 5/32 + 1/8$

= ${8 + 7 + 6 + 5 + 4}/32 = 30/32 = 15/16$

Remaining work = $1 - 15/16 = 1/16$

Now 15 men remain to work

15 men’s 1 day’s work= $15/1600$

Time taken to complete $1/16$ part of work

= $1600/15 × 1/16 = 20/3 = 6{2}/3$ days

Total time = $50 + 6{2}/3 = 56{2}/3$ days

Question : 4

A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?

a) 10 days

b) 6 days

c) 8 days

d) 12 days

Answer: (c)

Work done by (A + C) in 2 days

= $2(1/10 + 1/20) = 2({2 + 1}/20) = 6/20 = 3/10$

Remaining work = $1 - 3/10 = 7/10$

(B + C)’s 1 day’s work

= $1/15 + 1/20 = {4 + 3}/60 = 7/60$

Time taken by (B + C) to finish $7/10$ part of the work

= $60/7 × 7/10$ = 6 days

Total time = 2 + 6 = 8 days

Question : 5

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed?

a) 10 days

b) 9.6 days

c) 9 days

d) 12 days

Answer: (c)

Let the work be finished in x days.

According to the question,

A worked for x days while B worked for (x - 3) days

$x/18 + {x - 3}/12 = 1$

${2x + 3x - 9}/36 = 1$

5x - 9 = 36

5x = 45 ⇒ x = $45/5$ = 9

Hence, the work was completed in 9 days.

Using Rule 8
(i) If A can do a work in 'x' days and B can do the same work in 'y' days and when they started working together, B left the work 'm' days before completion then
total time taken to complete work is ${(y + m)x}/{x + y}$
(ii) A leaves the work 'm' days before its completion then total time taken to complete work is = ${(x + m)y}/{x + y}$

Here, x = 18, y = 12, m = 3

Total time taken = $({y + m}/{x + y})x$

= $({12 + 3}/{18 + 12})$ × 18 = 9 days

Question : 6

A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last ?

a) 20 days

b) 15 days

c) 6 days

d) 10 days

Answer: (d)

A’s 1 day’s work = $1/20$

A’s 4 days’ work = $4/20 = 1/5$

Remaining work = $1 - 1/5 = 4/5$

This part is completed by A and B together.

Now, (A + B)’s 1 day’s work = $1/20 + 1/12$

= ${3 + 5}/60 = 8/60 = 2/15$

Now, $2/15$ work is done by (A + B) in 1 day.

$4/5$ work is done in

= $15/2 × 4/5$ = 6 days.

Hence, the work lasted for 4 + 6 = 10 days.

Recently Added Subject & Categories For All Competitive Exams

Most Important Antonyms Vocabulary - IBPS Clerk Prelims 2024

Latest Antonyms multiple choice questions and answers with free PDFfor IBPS Clerk Prelims 2024. English Vocabulary practice exercise for all bank exam

17-May-2024 by Careericons

Continue Reading »

Syllogism Practice Questions Answers PDF - IBPS Clerk 2024

Practice Verbal Reasoning Syllogism multiple choice questions and answers with Fully solved explanation, PDF for the IBPS Clerk Prelims 2024 Bank Exam

16-May-2024 by Careericons

Continue Reading »

IBPS Clerk Prelims 2024 Synonyms Questions Solved Answers

Most important IBPS Clerk Prelims 2024 Synonyms and Antonyms multiple choice questions and answers with detailed solutions, English vocabulary PDF Download

14-May-2024 by Careericons

Continue Reading »

New Cloze Test Questions and Answers PDF - IBPS Clerk 2024

The most important Cloze Test questions with detailed answers for upcoming IBPS Clerk prelims 2024. Latest English verbal ability practice MCQs, PDF

13-May-2024 by Careericons

Continue Reading »