Practice Man leaves and joins - quantitative aptitude Online Quiz (set-1) For All Competitive Exams

Q-1)   8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

(a)

(b)

(c)

(d)

Explanation:

Using Rule 1
If $M_1$ men can finish $W_1$ work in $D_1$ days and $M_2$ men can finish $W_2$ work in $D_2$ days then, Relation is
${M_1D_1}/{W_1} = {M_2D_2}/{W_2}$ and
If $M_1$ men finish $W_1$ work in $D_1$ days, working $T_1$ time each day and $M_2$ men finish $W_2$ work in $D_2$ days, working $T_2$ time each day, then
${M_1D_1T_1}/{W_1} = {M_2D_2T_2}/{W_2}$

Work done by 8 men in 6 days

= $6/12 = 1/2$

Remaining work

= $1 - 1/2 = 1/2$

4 more men are engaged.

Total number of men = 8 + 4 = 12

By work and time formula

$W_1/{M_1D_1} = W_2/{M_2D_2}$, we have

$1/{8 × 12} = {1/2}/{12 × D_2}$

$D_2 = 1/2 × {8 × 12}/12$ = 4 days.


Q-2)   A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there ?

(a)

(b)

(c)

(d)

Explanation:

Originally, let there be x men

Now, more men, less days

(x + 6) : x : : 55 : 44

So, ${x + 6}/x = 55/44 = 5/4$

or 5x = 4x + 24 ⇒ x = 24

Using Rule 23
Some people finish a certain work in 'D' days. If there were 'a' less people, then the work would be completed in 'd'days more, what was the number of people initially?
Required number = $\text"a(D - d)"/\text"d"$ people

Here, D = 55, a = 6, d = 11

No of people initially = $\text"a(D - d)"/\text"d"$

= ${6(55 - 11)}/11$ = 24


Q-3)   A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in :

(a)

(b)

(c)

(d)

Explanation:

Work done by (A + B) in 1 day

= $1/15 + 1/10 = {2 + 3}/30 = 5/30 = 1/6$

(A + B)’s 2 days’ work = $2/6 = 1/3$

Remaining work = $1 - 1/3 = 2/3$

This part is done by A alone.

Since, one work is done by A in 15 days.

$2/3$ work is done in $15 × 2/3$ = 10 days.

Total number of days = 10 + 2 = 12 days

Using Rule 20,

Here, m = 15, n = 10, p =2

A alone completed the work in

= $\text"mn - p(m+n)"/ \text"n"$days

= ${15 × 10 - 2(15 + 10)}/10$

= ${150 - 50}/10$ = 10 days

Total time taken= 10 + 2 = 12 days


Q-4)   A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in

(a)

(b)

(c)

(d)

Explanation:

Work done by B in 9 days = $9/12 = 3/4$ part

Remaining work

= $1 - 3/4 = 1/4$ which is done by A

Time taken by A = $1/4 × 20$ = 5 days


Q-5)   A and B alone can complete work in 9 days and18 days respectively. They worked together; however 3 days before the completion of the work A left. In how many days was the work completed ?

(a)

(b)

(c)

(d)

Explanation:

Let the work be completed in x days.

According to the question,

A worked for (x –3) days, while B worked for x days.

${x - 3}/9 +x/18$ = 1

${2x - 6 + x}/18$ = 1

3x–6 = 18

3x = 18 + 6 = 24 ⇒ x = $24/3$ = 8 days

Using Rule 8,

Here, x = 9, y = 18, m = 3

Total time taken = ${(x + m)y}/{x + y}$

=${(9 + 3) × 18}/{9 + 18}$

= ${12 × 18}/27$ = 8 days


Q-6)   A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in :

(a)

(b)

(c)

(d)

Explanation:

Work done by (B + C) in 3 days.

= $3 × (1/9 + 1/12)$

= $1/3 + 1/4 = {4 + 3}/12 = 7/12$

Remaining work = $1 - 7/12 = 5/12$

This part of work is done by A alone.

Now, $1/24$ part of work is done by A in 1 day.

∴ $5/12$ part of work will be done by A in

= $24 × 5/12$ = 10 days.


Q-7)   A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?

(a)

(b)

(c)

(d)

Explanation:

Let the work be completed in x days.

According to the question,

${x - 5}/10 + {x - 3}/12 + x/15$ = 1

${6x - 30 + 5x - 15 + 4x}/60$ = 1

15x - 45 = 60

15x = 105 ⇒ x = $105/15$ = 7

Hence, the work will be completed in 7 days.


Q-8)   A and B can do a work in 45 days and 40 days respectively. They began the work together but A left after some time and B completed the remaining work in 23 days. After how many days of the start of the work did A leave ?

(a)

(b)

(c)

(d)

Explanation:

(A + B)’s 1 day’s work

= $(1/45 + 1/40) = {8 + 9}/360 = 17/360$

Work done by B in 23 days

= $1/40 × 23 = 23/40$

Remaining work = $1 - 23/40 = 17/40$

Now, $17/360$ work was done by (A + B) in 1 day

$17/40$ work was done by (A + B) in $1 × 360/17 × 17/40$ = 9 days.

Hence, A left after 9 days.

Using Rule 26
A and B can do a piece of work in x and y days, respectively. Both begin together but after some days.A leaves the job and B completed the remaining work in a days. After how many days did A leave?
Required time, t = $\text"(y - a)"/\text"(x + y)" × x$

Here, x = 45, y = 40, a = 23

Required time t= $\text"(y - a)"/\text"(x + y)" × x$

t = ${(40 - 23) × 45}/{45 + 40} = {17 × 45}/85$

t = 9 days


Q-9)   A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time, then B left the work. If A completed the rest of the work in 10 days, then B worked for

(a)

(b)

(c)

(d)

Explanation:

Let A and B worked together for x days

According to the question,

Part of work done by A for (x + 10) days

+ part of work done by B for x days = 1

${x + 10}/20 + x/30$ = 1

${3x + 30 + 2x}/60 = 1$

5x + 30 = 60

5x = 30 ⇒ x = $30/5$ = 6 days

Using Rule 20
A can do a certain work in 'm' days and B can do the same work in 'n' days. They worked together for 'P' days and after this A left the work, then in how many days did B alone do the rest of work ?
Required time = ${mn - P(m + n)}/m$ days
when after 'P' days B left the work, then in how many days did A alone do the rest of work?
Required time = ${mn - P(m + n)}/n$ days

Here, m =20, n= 30, p = x and time taken by A alone = 10

10 = ${mn - p(m + n)}/n$

10 = ${30 × 20 - x(30 + 20)}/30$

300 = 600 - x 50

50x = 300 x = 6

B worked for 6 days


Q-10)   A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave ?

(a)

(b)

(c)

(d)

Explanation:

Let A worked for x days.

According to question

$x/28 + (x + 17)/35 = 1$

${5x + 4(x + 17)}/140 = 1$

5x + 4x + 68 = 140

9x = 140 - 68 = 72

x = 8

∴ A worked for 8 days