Model 6  Efficiency of the worker Practice Questions Answers Test with Solutions & More Shortcuts

Question : 21 [SSC SAS 2010]

A and B together can complete a work in 15 days. A is 50% more efficient worker than B. How long will A take to complete the work alone ?

a) 22.5 days

b) 25 days

c) 21 days

d) 21.4 days

Answer: (b)

Ratio of the work of A and B done in 1 day = 3 : 2

[Since, B's work doen = x (let), then A's work done = ${x + 50}/100 x = 3/2 x$ So, (A : B)'s work done = $3/2 x : x$ or 3 : 2 ]

Since, Work done by A and B together in 1 day = $1/15$

A’s 1 day’s work = $1/15 × 3/5= 1/25$

Hence, A alone will finish the work in 25 days.

Using Rule 22,

Here, n = $3/2$ because A is 50% more efficient than B.

D = 15

Time taken by A = $({n + 1}/n)$D days

= $({{3/2} + 1}/{3/2}) × 15$ = 25 days

Question : 22 [SSC CGL Tier-II 2016]

A man does double the work done by a boy in the same time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 men in 8 days is

a) 8$4/5$

b) 4

c) 16

d) 7$3/11$

Answer: (c)

According to the question,

1 man ≡ 2 boys

3 men + 4 boys ≡ (3 + 2) men ≡ 5 men

$M_1D_1 = M_2D_2$

5 × $D_1$ = 10 × 8

$D_1 = {10 × 8}/5$ = 16 days

Question : 23 [SSC CHSL 2011]

5 men and 2 women working together can do four times as much work per hour as a man and a woman together. The work done by a man and a woman should be in the ratio :

a) 4 : 1

b) 1 : 2

c) 2 : 1

d) 1 : 3

Answer: (c)

5m + 2w = 4m + 4w ⇒ m = 2w

Required ratio = 2 : 1

Question : 24 [SSC CGL Tier-1 2011]

A and B together can do a work in 12 days. B and C together do it in 15 days. If A’s efficiency is twice that of C, then the days required for B alone to finish the work is

a) 15 days

b) 60 days

c) 30 days

d) 20 days

Answer: (d)

(A + B)’s 1 day’s work = $1/12$ ... (i)

(B + C)’s 1 day’s work = $1/15$ ... (ii)

Difference between A and C’s 1 day’s work

= $1/12 - 1/15 = {5 - 4}/60 = 1/60$

If A alone completes the work in x days, C will do the same in 2x days.

$1/x - 1/{2x} = 1/60$

${2 - 1}/{2x} = 1/60$

$1/{2x} = 1/60 ⇒ x = 30$

B’s 1 day’s work

= $1/12 - 1/30$ [From equation (i)]

= ${5 - 2}/60 = 3/60 = 1/20$

Hence, B alone will complete the work in 20 days.

Question : 25 [SSC CGL Tier-I 2016]

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is

a) 24 days

b) 20 days

c) 21 days

d) 22 days

Answer: (a)

A is twice as good as B.

Time taken by A = x days

Time taken by B = 2x days

According to the question,

$1/x + 1/{2x} = 1/16$

${2 + 1}/{2x} = 1/16$

$3/x = 1/8$

x = 3 × 8 = 24 days

IMPORTANT quantitative aptitude EXERCISES

Model 6  Efficiency of the worker Shortcuts »

Click to Read...

Model 6  Efficiency of the worker Online Quiz

Click to Start..

Recently Added Subject & Categories For All Competitive Exams

New 150+ Percentage Questions For IBPS Clerk Prelims 2024

Free Top Percentage Quants Aptitude based Multiple Choice Questions and Answers Practice Test Series, Quiz PDF & Mock Test for IBPS Clerk Prelims 2024 Exam

04-May-2024 by Careericons

Continue Reading »

Classification Reasoning MCQ For IBPS Clerk Prelims 2024

Most Important 100+ Classification based Verbal Reasoning Ability Multiple choice questions and answers PDF, Free New Mock tests For IBPS Clerk Prelims 2024

03-May-2024 by Careericons

Continue Reading »

Ratio and Proportion Questions with Solutions, IBPS Clerk

New Ratio and Proportion Quants Aptitude based Multiple Choice Questions and Answers Practice Test Series, Quiz & Mock Test for IBPS Clerk Prelims 2024 Exam

02-May-2024 by Careericons

Continue Reading »

Top Analogy Reasoning Ability For IBPS Clerk Prelims 2024

Most Important Analogy based Verbal Reasoning Multiple choice questions and answers practice quiz series PDF, Free New Mock tests For IBPS Clerk Prelims 2024

01-May-2024 by Careericons

Continue Reading »