Question : 16 [SSC CGL Tier-I 2016]

Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. The ratio between the capacity of a man and a woman is

a) 5 : 3

b) 3 : 4

c) 4 : 3

d) 5 : 7

Answer: (c)

20 women complete 1 work in 16 days.

16 men complete same work in 15 days

16 × 15 men ≡ 20 × 16 women

3 men ≡ 4 women

∴ Required ratio = 4 : 3

Question : 17 [SSC CGL Tier-I 2012]

3 men and 4 boys can complete a piece of work in 12 days. 4 men and 3 boys can do the same work in 10 days. Then 2 men and 3 boys can finish the work in number of days is

a) 8 days

b) 17$1/2$ days

c) 5$5/11$ days

d) 22 days

Answer: (b)

12 (3 men + 4 boys) = 10 (4 men + 3 boys)

36 men + 48 boys = 40 men + 30 boys

4 men = 18 boys or 2 men = 9 boys

4 men + 3 boys

= 21 boys who do the work in 10 days

and, 2 men + 3 boys = 12 boys

$M_1D_1 = M_2D_2$

21 × 10 = 12 × $D_2$

$D_2 = {21 × 10}/12 = 35/2 = 17{1}/2$ days

Using Rule 11,

Here, $A_1 = 3, B_1 = 4, D_1 = 12$

$A_2 = 4, B_2 = 3, D_2$ = 10

$A_3 = 2, B_3$ = 3

Required time = ${D_1D_2(A_1B_2 - A_2B_1)}/{D_1(A_1B_3 - A_3B_1) - D_2(A_2B_3 - A_3 B_2)}$ days

= ${12 × 10(3 × 3 - 4 × 4)}/{12(3 × 3 - 2 × 4) - 10(4 × 3 - 2 × 3)}$

= ${-120 × 7}/{12 - 60} = {-840}/{-48} = 70/4$

= $35/2 = 17{1}/2$ days

Question : 18 [SSC MTS 2017]

3 men and 5 women can do a work in 14 days while 5 men can do it in 14 days. 5 men and 5 women can complete the work in

a) 10 days

b) 13 days

c) 11 days

d) 12 days

Answer: (a)

5 men can do 1 work in 14 days.

3 men will do $3/5$ work in 14 days.

Remaining work = $1 - 3/5 = 2/5$

5 women do $2/5$ work in 14 days.

Time taken by 5 women in doing 1 work

= ${14 × 5}/2 = 35$ days

(5 men + 5 women)’s 1 day’s work

= $1/14 + 1/35 = {5 + 2}/70 = 7/70 = 1/10$

∴Required time = 10 days.

Question : 19 [SSC CPO S.I. 2010]

One man and one woman together can complete a piece of work in 8 days. A man alone can complete the work in 10 days. In how many days can one woman alone complete the work ?

a) 40 days

b) $140/9$ days

c) 30 days

d) 42 days

Answer: (a)

Work done by 1 woman in 1 day

= $1/8 - 1/10 = {5 - 4}/40 = 1/40$

One woman will complete the work in 40 days.

Using Rule 4
If A alone can do a certain work in 'x' days and A and B together can do the same work in 'y' days, then B alone can do the same work in $({xy}/{x - y})$ days.

Here, x = 10 and y = 8

Woman can do work in = $({xy}/{x - y})$ days

= $({10 × 8}/{10 - 8})$ = 40 days

Question : 20 [SSC CGL Prelim 2004]

4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it ?

a) 40 days

b) 50 days

c) 45 days

d) 35 days

Answer: (a)

Let 1 man’s 1 day’s work = x and

1 woman’s 1 day’s work = y

Then, 4x + 6y = $1/8$ and

$3x + 7y = 1/10$

From both equations,

we get y = $1/400$

10 women’s 1 day’s work = $10/400 = 1/40$

10 women will finish the work in 40 days.

Using Rule 11,

$A_1 = 4, B_1 = 6, D_1$ = 8

$A_2 = 3, B_2 = 7, D_2$ = 10

$A_3 = 0, B_3$ = 10

Required time = ${D_1D_2(A_1B_2 - A_2B_1)}/{D_1(A_1B_3 - A_3B_1) - D_2(A_2B_3 - A_3 B_2)}$

= ${8 × 10(4 × 7 - 3 × 6)}/{8(4 × 10 - 0 × 6) - 10(3 × 10 - 0 × 7)}$

= ${80 × 10}/20$ = 40 days

IMPORTANT quantitative aptitude EXERCISES

Model 4  Working with Man, Woman, Child Shortcuts »

Click to Read...

Model 4  Working with Man, Woman, Child Online Quiz

Click to Start..

Recently Added Subject & Categories For All Competitive Exams

Ratio and Proportion Questions with Solutions, IBPS Clerk

New Ratio and Proportion Quants Aptitude based Multiple Choice Questions and Answers Practice Test Series, Quiz & Mock Test for IBPS Clerk Prelims 2024 Exam

02-May-2024 by Careericons

Continue Reading »

Top Analogy Reasoning Ability For IBPS Clerk Prelims 2024

Most Important Analogy based Verbal Reasoning Multiple choice questions and answers practice quiz series PDF, Free New Mock tests For IBPS Clerk Prelims 2024

01-May-2024 by Careericons

Continue Reading »

SSC STENO: Mensuration Area & Volume Questions Test PDF

Free Mensuration Area and Volume Aptitude-based Practice multiple questions with solutions, Quiz, Full Mock Test & PDF for SSC Steno (Grade C & D) 2024 Exam

30-Apr-2024 by Careericons

Continue Reading »

SSC STENO: Speed Time and Distance MCQ Questions Test PDF

Free Time and Distance Aptitude-based Practice multiple questions with solutions, Quiz series, Mock Test & Download PDF for SSC Steno (Grade C & D) 2024 Exam

29-Apr-2024 by Careericons

Continue Reading »