Model 1 Basics on Time & Work Practice Questions Answers Test with Solutions & More Shortcuts

Question : 26 [SSC Constable (GD) 2012]

A, B and C individually can do a work in 10 days, 12 days and 15 days respectively. If they start working together, then the number of days required to finish the work is

a) 2 days

b) 4 days

c) 16 days

d) 8 days

Answer: (b)

Work done by A, B and C in 1 day

= $1/10 + 1/12 + 1/15 = {6 + 5 + 4}/60$

= $15/60 = 1/4$

Required time = 4 days

Using Rule 3,

Time Taken = ${xyz}/{xy + yz + zx}$

= ${10 × 12 × 15}/{10 × 12 + 12 × 15 + 15 × 10}$

= $1800/{120 + 180 + 150}$

= $1800/450$ = 4 days

Question : 27 [SSC GL Tier-I 2013]

A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :

a) 15$2/3$ days

b) 10 days

c) 5 days

d) 7$5/6$ days

Answer: (b)

According to question,

A and B can do a work in 12 days

(A + B)'s one day's work = $1/12$

Similarly, (B + C)'s one day's work = $1/15$

and (C + A)'s one day's work = $1/20$

On adding all three,

2 (A + B + C)'s one days's work

= $1/12 + 1/15 + 1/20 = {10 + 8 + 6}/120 = 1/5$

(A + B + C)'s one days's work = $1/10$

A, B and C together can finish the whole work in 10 days.

Using Rule 5
If A and B can do a work in 'x' days, B and C can do the same work in 'y' days, C and A can do the same work in 'z' days. Then total time taken, when A, B and C
work together =$2/{(1/x + 1/y + 1/z)}$ OR ${2xyz}/{xy + yz + zx}$ days

Time taken = ${2 × 12 × 15 × 20}/{12 × 15 + 15 × 20 + 20 × 12}$

= ${24 × 300}/{180 + 300 + 240} = 7200/720$ = 10 days.

Question : 28 [SSC GL Tier-I 2013]

A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work?

a) 60 days

b) 30 days

c) 10 days

d) 20 days

Answer: (b)

(P + Q)’s 1 day’s work = $1/12$ ...(i)

(Q + R)’s 1 day’s work = $1/15$ ...(ii)

(R + P)’s 1 day’s work = $1/20$ ...(iii)

Adding all three equations,

2 (P + Q + R)’s 1 day’s work = $1/12 + 1/15 + 1/20$

${5 + 4 + 3}/60 = 12/60 = 1/5$

(P + Q + R)’s 1 day’s work = $1/10$ ...(iv)

P’s 1 day’s work = $1/10 - 1/15 = {3 - 2}/30 = 1/30$

P alone will complete the work in 30 days.

Question : 29 [SSC CGL Prelim 2000]

A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?

a) 18 days

b) 9 days

c) 4 days

d) 6 days

Answer: (c)

According to question,

10 men’s one day’s work = $1/12$

1 man one day’s work =$1/{12 × 10} = 1/120$

Similarly, 1 woman one day’s work = $1/{6 × 10} = 1/60$

(1 man + 1 woman)’s one day’s work = $1/120 + 1/60$

= ${1 + 2}/120 = 3/120 = 1/40$

(10 men + 10 women)’s one day’s work = $10/40 = 1/4$

Therefore, both the teams can finish the whole work in 4 days.

Question : 30 [SSC CPO S.I.2009]

A and B can do a piece of work in 10 days. B and C can do it in 12 days. C and A in 15 days. In how many days will C finish it alone ?

a) 60 days

b) 40 days

c) 24 days

d) 30 days

Answer: (b)

(A + B)'s 1 day's work = $1/10$ ... (i)

(B + C)'s 1 day’s work = $1/12$ ... (ii)

(C + A)’s 1 day’s work = $1/15$ ... (iii)

On adding all these,

2(A + B + C)’s 1 day’s work = $1/10 + 1/12 + 1/15$

= ${6 + 5 + 4}/60 = 1/4$

(A + B + C)’s 1 day’s work = $1/8$ … (iv)

C’s 1 day’s work = $1/8 - 1/10 = {5 - 4}/40 = 1/40$

C will finish the work in 40 days.

Using Rule 19,

C alone can do in = ${2 × 10 × 12 × 15}/{10 × 12 - 12 × 15 + 10 × 15}$

= ${240 × 15}/{120 - 180 + 150} = {240 × 15}/90$ = 40 days

IMPORTANT quantitative aptitude EXERCISES

Model 1 Basics on Time & Work Shortcuts »

Click to Read...

Model 1 Basics on Time & Work Online Quiz

Click to Start..

Recently Added Subject & Categories For All Competitive Exams

New 100+ Compound Interest MCQ with Answers PDF for IBPS

Compound Interest verbal ability questions and answers solutions with PDF for IBPS RRB PO. Aptitude Objective MCQ Practice Exercises all competitive exams

02-Jul-2024 by Careericons

Continue Reading »

100+ Mixture and Alligation MCQ Questions PDF for IBPS

Most importantly Mixture and Alligation multiple choice questions and answers with PDF for IBPS RRB PO. Aptitude MCQ Practice Exercises all Bank Exams

02-Jul-2024 by Careericons

Continue Reading »

IBPS Profit and Loss Questions Solved Problems with PDF

Most important Profit and Loss multiple choice questions and answers with PDF for IBPS RRB PO. 100+ Aptitude MCQ Practice Exercises all competitive exams

28-Jun-2024 by Careericons

Continue Reading »

100+ Average Aptitude Questions Answers solutions MCQ PDF

New Average multiple choice questions and answers with PDF for IBPS RRB PO. 100+ Quantitative Aptitude MCQ Practice Exercises all competitive exams

28-Jun-2024 by Careericons

Continue Reading »