Model 1 Basics on Time & Work Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : If A and B together can finish a piece of work in 20 days, B and C in 10 days and C and A in 12 days, then A, B, C jointly can finish the same work in

(a) $7/60$ days

(b) 8$4/7$ days

(c) 4$2/7$ days

(d) 30 days

The correct answers to the above question in:

Answer: (b)

(A + B)’s 1 day’s work = $1/20$

(B + C)’s 1 day’s work = $1/10$

(C + A)’s 1 day’s work = $1/12$

On adding all three,

2 (A + B + C)’s 1 day’s work = $1/20 + 1/10 + 1/12$

= ${3 + 6 + 5}/60 = 14/60 = 7/30$

(A + B + C)’s 1 day’s work = $7/60$

Hence, the work will be completed in $60/7 = 8{4}/7$ days.

Using Rule 5,

Time taken = ${2xyz}/{xy + yz + zx}$

= ${2 × 20 × 10 × 12}/{20 × 10 + 10 × 12 + 12 × 20}$

= $4800/{200 + 120 + 240}$

= $4800/560 = 60/7 = 8{4}/7$ days

Practice time & work (Model 1 Basics on Time & Work) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more basics on time and work Based Quantitative Aptitude Questions and Answers

Question : 1

A and B together can do a piece of work in 5 days and A alone can do it in 8 days. B alone can do the same piece of work in

a) 16$4/5$ days

b) 13$1/3$ days

c) 11$1/3$ days

d) 12$3/5$ days

Answer: (b)

(A + B)’s 1 day’s work = $1/5$

A’s 1 day’s work = $1/8$

B’s 1 day’s work = $1/5 - 1/8$

= ${8 - 5}/40 = 3/40$

B alone will complete the work in $40/3 = 13{1}/3$ days.

Using Rule 4,

Time taken by B = ${5 × 8}/{8 - 5}$

= $40/3 = 13{1}/3$ days

Question : 2

A and B can do a piece of work in 8 days, B and C can do it in 24 days, while C and A can do it in 8$4/7$ days. In how many days can C do it alone?

a) 10 days

b) 30 days

c) 60 days

d) 40 days

Answer: (c)

(A + B)’s 1 day’s work = $1/8$

(B + C)’s 1 day’s work = $1/24$

(C + A)’s 1 day’s work = $7/60$

On adding all three,

2 (A + B + C)’s 1 day’s work = $1/8 + 1/24 + 7/60$

= ${15 + 5 + 14}/120 = 34/120$

(A + B + C)’s 1 day’s work = $17/120$

C’s 1 day’s work

= $17/120 - 1/8 = {17 - 15}/120 = 1/60$

C alone will complete the work in 60 days.

Using Rule 19,

C alone can do in= ${2xyz}/{xy - yz + zx}$

= ${2 × 8 × 24 × 60/7}/{8 × 24 - 24 × 60/7 + 60/7 × 8$

= ${23040/7}/{192 - 1440/7 + 480/7}$

= ${23040/7}/{{1344 - 1440 + 480}/7}$

= $23040/7 × 7/384$ = 60 days

Question : 3

A, B and C individually can do a work in 10 days, 12 days and 15 days respectively. If they start working together, then the number of days required to finish the work is

a) 2 days

b) 4 days

c) 16 days

d) 8 days

Answer: (b)

Work done by A, B and C in 1 day

= $1/10 + 1/12 + 1/15 = {6 + 5 + 4}/60$

= $15/60 = 1/4$

Required time = 4 days

Using Rule 3,

Time Taken = ${xyz}/{xy + yz + zx}$

= ${10 × 12 × 15}/{10 × 12 + 12 × 15 + 15 × 10}$

= $1800/{120 + 180 + 150}$

= $1800/450$ = 4 days

Question : 4

A and B together can do a piece of work in 10 days. A alone can do it in 30 days. The time in which B alone can do it is

a) 20 days

b) 15 days

c) 10 days

d) 12 days

Answer: (b)

(A + B)’s 1 day’s work = $1/10$

A’s 1 day’s work = $1/30$

B’s 1 day’s work = $1/10 - 1/30$

= ${3 - 1}/30 = 2/30 = 1/15$

Hence, B, alone can complete the work in 15 days.

Using Rule 4
If A alone can do a certain work in 'x' days and A and B together can do the same work in 'y' days, then B alone can do the same work in $({xy}/{x - y})$ days.

Time taken by B = ${30 × 10}/{30 - 10}$ = 15 days

Question : 5

A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?

a) 150 days

b) 120 days

c) 80 days

d) 100 days

Answer: (b)

(A + B)’s 1 day’s work = $1/72$

(B + C)’s 1 day’s work = $1/120$

(C + A)’s 1 day’s work = $1/90$

Adding all three,

2(A + B + C)’s 1 day’s work = $1/72 + 1/120 + 1/90$

= ${5 + 3 + 4}/360 = 12/360 = 1/30$

(A + B + C)’s 1 day’s work = $1/60$

Now, A’s 1 day’s work = (A + B + C)’s 1 day’s work - (B + C)’s 1 day’s work

= $1/60 - 1/120 = {2 - 1}/120 = 1/120$

A alone can complete the work in 120 days.

Using Rule 19,

A alone can do in

= ${2 × 72 × 120 × 90}/{72 × 120 + 120 × 90}$ - 72 × 90

= ${2 × 72 × 120 × 90}/{8640 + 10800}$ - 6480

= ${144 × 10800}/12960$ = 120 days

Question : 6

If A and B together can complete a work in 18 days, A and C together in 12 days and B and C together in 9 days, then B alone can do the work in

a) 40 days

b) 30 days

c) 18 days

d) 24 days

Answer: (d)

(A + B)’s 1 day’s work = $1/18$

(B + C)’s 1 day’s work = $1/9$

(A + C)’s 1 day’s work = $1/12$

Adding all the above three,

2 (A + B + C)’s 1 day’s work = $1/18 + 1/9 + 1/12$

= ${2 + 4 + 3}/36 = 9/36 = 1/4$

(A + B + C)’s 1 day’s work = $1/8$

B’s 1 day’s work = (A + B + C)’s 1 day’s work - (A + C)’s 1 day’s work

= $1/8 - 1/12 = {3 - 2}/24 = 1/24$

Hence, B alone can do the work in 24 days.

Using Rule 19,

B alone can do in = ${2 × 18 × 9 × 12}/{-18 × 9 + 12 × 9 + 12 × 18}$

= ${36 × 108}/{-162 + 108 + 216} = {36 × 108}/162$ = 24 days

Recently Added Subject & Categories For All Competitive Exams

SSC STENO: Speed Time and Distance MCQ Questions Test PDF

Free Time and Distance Aptitude-based Practice multiple questions with solutions, Quiz series, Mock Test & Download PDF for SSC Steno (Grade C & D) 2024 Exam

29-Apr-2024 by Careericons

Continue Reading »

SSC STENO: Time & Work Questions Solved Problems with PDF

Free Time and work Aptitude-based Practice multiple questions with solutions, Quiz series, Mock Test & Downloadable PDF for SSC Steno (Grade C & D) 2024 Exam

27-Apr-2024 by Careericons

Continue Reading »

SSC STENO 2024: Free Reading Comprehension MCQ Test PDF

Top Reading Comprehension English Section-wise multiple choice questions and answers, Full Mock Test Series & Online Quiz for SSC Steno Grade C & D 2024 Exam

26-Apr-2024 by Careericons

Continue Reading »

Free Percentage Questions Answers for SSC STENO 2024 Exam

Important Top Percentage Aptitude-based multiple choice questions and answers practice quiz series, Online Mock Test PDF for SSC Steno Grade C & D 2024 Exam

25-Apr-2024 by Careericons

Continue Reading »