Model 1 Basics on Time & Work Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : A and B can do a piece of work in 10 days. B and C can do it in 12 days. A and C can do it in 15 days. How long will A take to do it alone ?

(a) 30 days

(b) 40 days

(c) 24 days

(d) 20 days

The correct answers to the above question in:

Answer: (c)

(A+B)’s 1 day’s work = $1/10$

(B + C)’s 1 day’s work = $1/12$

(C + A)’s 1 day’s work = $1/15$

On adding all three,

2(A + B + C)’s 1 day’s work = $1/10 + 1/12 + 1/15$

= ${6 + 5 + 4}/60 = 15/60 = 1/44$

(A + B + C)’s 1 day’s work = $1/8$

A’s 1 day’s work = $1/8 - 1/12$

= ${3 - 2}/24 = 1/24$

A will complete the work in 24 days.

Using Rule 19,

A alone can do in = ${2 × x × y × z}/{xy + yz - zx}$

= ${2 × 10 × 12 × 15}/{10 × 12 + 12 × 15 - 15 × 10}$

= $3600/{120 + 180 - 150}$

= $3600/150$ = 24 days

Practice time & work (Model 1 Basics on Time & Work) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more basics on time and work Based Quantitative Aptitude Questions and Answers

Question : 1

A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in

a) 4 days

b) 3${3}/7$ days

c) $1/4$ day

d) $7/24$ day

Answer: (b)

A’s 1 day’s work = $1/24$

B’s 1 day’s work = $1/6$

C’s 1 day’s work = $1/12$

(A + B + C)’s 1 day’s work

=$1/24 + 1/6 + 1/12 = {1 + 4 + 2}/24 = 7/24$

The work will be completed by them in $24/7$ i.e., 3$3/7$ days

Using Rule 3
If A can do a work in 'x' days, B can do the same work in 'y' days, C can do the same work in 'z' days then, total time taken by A, B and C to complete the work together = $1/{1/x + 1/y + 1/z} = {xyz}/{xy + yz + zx}$and
If workers are more than 3 then total time taken by A, B, C ...... so on to complete the work together = $1/{1/x + 1/y + 1/z + ...}$

Time taken = ${24 × 6 × 12}/{24 × 6 + 6 × 12 + 24 × 12}$

= $1728/{144 + 72 + 288}$

= $1728/504 = 24/7 = 3{3}/7$ days

Question : 2

A and B can do a piece of work in 72 days. B and C can do it in 120 days, A and C can do it in 90 days. In how many days all the three together can do the work ?

a) 150 days

b) 60 days

c) 80 days

d) 100 days

Answer: (b)

(A+B)’s 1 day’s work = $1/72$,

(B+C)’s 1 day’s work = $1/120$,

(C+A)’s 1 day’s work = $1/90$

On adding all three

2 (A + B + C)'s 1 days work = $1/72 + 1/120 + 1/90$

= ${5 + 3 + 4}/360 = 1/30$

(A+B+C)’s 1 day’s work = $1/60$

(A+B+C) will do the work in 60 days.

Using Rule 5,

Time taken = ${2 × 72 × 120 × 90}/{72 × 120 + 120 × 90 + 72 × 90}$

= $1555200/{8640 + 10800 + 6480}$

= $1555200/25920$ = 60 days

Question : 3

If A and B together can complete a work in 18 days, A and C together in 12 days and B and C together in 9 days, then B alone can do the work in

a) 40 days

b) 30 days

c) 18 days

d) 24 days

Answer: (d)

(A + B)’s 1 day’s work = $1/18$

(B + C)’s 1 day’s work = $1/9$

(A + C)’s 1 day’s work = $1/12$

Adding all the above three,

2 (A + B + C)’s 1 day’s work = $1/18 + 1/9 + 1/12$

= ${2 + 4 + 3}/36 = 9/36 = 1/4$

(A + B + C)’s 1 day’s work = $1/8$

B’s 1 day’s work = (A + B + C)’s 1 day’s work - (A + C)’s 1 day’s work

= $1/8 - 1/12 = {3 - 2}/24 = 1/24$

Hence, B alone can do the work in 24 days.

Using Rule 19,

B alone can do in = ${2 × 18 × 9 × 12}/{-18 × 9 + 12 × 9 + 12 × 18}$

= ${36 × 108}/{-162 + 108 + 216} = {36 × 108}/162$ = 24 days

Question : 4

A and B can complete a piece of work in 30 days, B and C in 20 days, while C and A in 15 days. If all of them work together, the time taken in completing the work will be

a) 13$1/3$ days

b) 12$2/3$ days

c) 10 days

d) 12 days

Answer: (a)

Work done by (A + B) in 1 day = $1/30$

Work done by (B + C) in 1 day = $1/20$

Work done by (C + A) in 1 day = $1/15$

On adding,

Work done by 2 (A +B + C) in 1 day

= $1/30 + 1/20 + 1/15 = {2 + 3 + 4}/60$

= $9/60 = 3/20$

Work done by (A + B + C) in 1 day = $3/40$

(A + B + C) will do the work in $40/3 = 13{1}/3$ days

Using Rule 5,

Time taken = ${2 × 30 × 20 × 15}/{30 × 20 + 20 × 15 + 15 × 30}$

= $18000/{600 + 300 + 450}$

= $18000/1350 = 13{1}/3$ days

Question : 5

A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in

a) 7 days

b) 6 days

c) 4 days

d) 5 days

Answer: (b)

(A + B)’s 1 day’s work = $1/8$

(B + C)’s 1 day’s work = $1/12$

(C + A)’s 1 day’s work = $1/8$

On adding,

2 (A + B + C)’s 1 day’s work = $1/8 + 1/12 + 1/8$

${3 + 2 + 3}/24 = 8/24 = 1/3$

(A + B + C)’s 1 day’s work = $1/6$

Hence, the work will be completed in 6 days.

Method 2 :

Time = ${2xyz}/{xy + yz + zx}$

(Here, x = 8, y = 12; z = 8)

= ${2 × 8 × 12 × 8}/{96 + 96 + 64}$

${2 × 8 × 12 × 8}/256$ = 6 days.

Using Rule 5,

Time taken = ${2 × 8 × 12 × 8}/{8 × 12 + 12 × 8 + 8 × 8}$

= ${16 × 96}/{96 + 96 + 64} = {16 × 96}/256$ = 6 days

Question : 6

While working 7 hours a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, working 8 hours a day ?

a) 3.6 days

b) 2.5 days

c) 3 days

d) 4 days

Answer: (c)

A alone can complete the work in 42 days working 1 hour daily. Similarly, B will take 56 days working 1 hour daily.

A 's 1 day's work = $1/42$

B 's 1 day's work = $1/56$

(A + B) 's 1 day's work = $1/42 + 1/56 = {4 + 3}/168 = 7/168$

Time taken by (A + B) working 8 hours daily

= $168/{7 × 8}$ = 3 days

Using Rule 21
If a man can do a certain work in '$d_1$' daysworking '$h_1$' hours in a days, while another man can do the same work in '$d_2$' days working '$h_2$' hours in a day. Whenthey work together everyday 'h' hours, then in how many days work will complete?
Required time = $[{({h_1d_1}) × ({h_2d_2})}/{h_1d_1 + h_2d_2}] 1/h$

Here, $h_1$ = 7 hours, $h_2$ = 7 hours, $d_1$ = 6 days, $d_2$ = 8 days, h = 8 hours

Required Time = $[{({7 × 6}) × ({7 × 8})}/{7 × 6 + 7 × 8}] × 1/8$

= ${42 × 56}/98 × 1/8 = 2352/98 × 1/8 = 24/8$ = 3 days

Recently Added Subject & Categories For All Competitive Exams

SSC STENO: Time & Work Questions Solved Problems with PDF

Free Time and work Aptitude-based Practice multiple questions with solutions, Quiz series, Mock Test & Downloadable PDF for SSC Steno (Grade C & D) 2024 Exam

27-Apr-2024 by Careericons

Continue Reading »

SSC STENO 2024: Free Reading Comprehension MCQ Test PDF

Top Reading Comprehension English Section-wise multiple choice questions and answers, Full Mock Test Series & Online Quiz for SSC Steno Grade C & D 2024 Exam

26-Apr-2024 by Careericons

Continue Reading »

Free Percentage Questions Answers for SSC STENO 2024 Exam

Important Top Percentage Aptitude-based multiple choice questions and answers practice quiz series, Online Mock Test PDF for SSC Steno Grade C & D 2024 Exam

25-Apr-2024 by Careericons

Continue Reading »

Free Antonyms (English) MCQ Test for SSC STENO 2024 Exam

Top Antonyms General English Section-based multiple choice questions and answers, Free Full Test Series & Online Quiz PDF for SSC Steno Grade C & D 2024 Exam

24-Apr-2024 by Careericons

Continue Reading »