Model 3 Man leaves & joins Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately with A beginning, the work would be completed in

(a) 10$1/2$ days

(b) 10$1/4$ days

(c) 10$1/3$ days

(d) 10$2/3$ days

The correct answers to the above question in:

Answer: (b)

Part of work done by A and B in first two days

= $1/9 + 1/12 = {4 - 3}/36 = 7/36$

Part of work done in first 10 days = $35/36$

Remaining work = $1 - 35/36 = 1/36$

Now it is the turn of A.

Time taken by A

= $1/36 × 9 = 1/4$ day

Total time = $10 + 1/4 = 10{1}/4$ days

Practice time & work (Model 3 Man leaves & joins) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more man leaves and joins Based Quantitative Aptitude Questions and Answers

Question : 1

A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?

a) 8 days

b) 10 days

c) 13 days

d) 6 days

Answer: (c)

(A+B)’s 2 days’ work = $2(1/12 + 1/18) = 10/36$

Remaining work = $1 - 10/36 = 26/36$

Time taken by B to complete $26/36$ part of work

= $26/36$ × 18 = 13 days

Using Rule 20,

Here, m = 12, n = 18, p = 2

Time taken by B = $\text"mn - p(m+n)"/ \text"m"$

= ${12 × 18 - 2(12 + 18)}/12$

= ${216 - 60}/12$ = 13 days

Question : 2

A and B together can complete a work in 8 days. B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work ?

a) 18 days

b) 16 days

c) 20 days

d) 15 days

Answer: (b)

Time taken by A

= ${8 × 12}/128 = {8 × 12}/4 = 24$ days

Work done of by B = $4/12 = 1/3$

Remaining work = $1 - 1/3 = 2/3$

Since, A can complete a work in 24 days

A can complete $2/3$ part of work in 24 × $2/3$ = 16 days

Question : 3

A and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then the total number of days needed for the completion of the work is :

a) 5 days

b) 6 days

c) 9 days

d) 4 days

Answer: (b)

A’s one day’s work = $1/6$

B’s one day’s work = $1/12$

(A + B)’s one day’s work = $1/6 + 1/12 = {2 + 1}/12 = 1/4$

(A + B)’s three day’s work = $3/4$

Remaining work = $1 - 3/4 = 1/4$

Total required number of days

= $1/4 × 12/1 + 3$ = 3 + 3 = 6 days

Using Rule 20,

Here, m = 6, n= 12, and p = 3

Time taken by B = $\text"mn - p(m+n)"/ \text"m"$

= ${6 × 12 - (6 + 12) × 3}/6 = {72 - 54}/6$ = 3 days

Total number of days taken to finish the works = 6 days

Recently Added Subject & Categories For All Competitive Exams

100+ Quadratic Equation Questions Answers PDF for Bank

Quadratic Equation multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams

03-Jul-2024 by Careericons

Continue Reading »

IBPS Aptitude Linear Equations MCQ Questions Answers PDF

Linear equations multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams

03-Jul-2024 by Careericons

Continue Reading »

New 100+ Compound Interest MCQ with Answers PDF for IBPS

Compound Interest verbal ability questions and answers solutions with PDF for IBPS RRB PO. Aptitude Objective MCQ Practice Exercises all competitive exams

02-Jul-2024 by Careericons

Continue Reading »

100+ Mixture and Alligation MCQ Questions PDF for IBPS

Most importantly Mixture and Alligation multiple choice questions and answers with PDF for IBPS RRB PO. Aptitude MCQ Practice Exercises all Bank Exams

02-Jul-2024 by Careericons

Continue Reading »