Model 3 Man leaves & joins Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in :

(a) 6 days

(b) 10 days

(c) 10$1/2$ days

(d) 5 days

The correct answers to the above question in:

Answer: (b)

Work done by (B + C) in 3 days.

= $3 × (1/9 + 1/12)$

= $1/3 + 1/4 = {4 + 3}/12 = 7/12$

Remaining work = $1 - 7/12 = 5/12$

This part of work is done by A alone.

Now, $1/24$ part of work is done by A in 1 day.

∴ $5/12$ part of work will be done by A in

= $24 × 5/12$ = 10 days.

Practice time & work (Model 3 Man leaves & joins) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more man leaves and joins Based Quantitative Aptitude Questions and Answers

Question : 1

A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in

a) 15$2/3$ days

b) 16$1/3$ days

c) 18$2/3$ days

d) 14$1/3$ days

Answer: (d)

A’s 1 day’s work = $1/12$

B’s 1 day’s work = $1/18$

Part of work done by A and B in first two days

= $1/12 + 1/18 = {3 - 2}/36 = 5/36$

Part of work done by A and B in 14 days = $35/36$

[14 days to be taken randomly]

Remaining work = $1 - 35/36 = 1/36$

Now A will work for 15th day.

A will do the $1/36$ work in $1/36 × 12 = 1/3$ day.

Total Work will be done in $14{1}/3$ days.

Question : 2

A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?

a) 60 days

b) 48 days

c) 54 days

d) 50 days

Answer: (a)

(A+B)’s 1 day’s work = $1/30$

(A + B)’s 20 day’s work = $20/30 = 2/3$

Remaining work = $1 - 2/3 = 1/3$

Now, $1/3$ part of work is done by A in 20 days.

Whole work will be done by A alone in 20 × 3 = 60 days.

Question : 3

A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?

a) 5 days

b) 7 days

c) 8 days

d) 4 days

Answer: (b)

Let the work be completed in x days.

According to the question,

${x - 5}/10 + {x - 3}/12 + x/15$ = 1

${6x - 30 + 5x - 15 + 4x}/60$ = 1

15x - 45 = 60

15x = 105 ⇒ x = $105/15$ = 7

Hence, the work will be completed in 7 days.

Question : 4

A and B alone can complete work in 9 days and18 days respectively. They worked together; however 3 days before the completion of the work A left. In how many days was the work completed ?

a) 8 days

b) 6 days

c) 5 days

d) 13 days

Answer: (a)

Let the work be completed in x days.

According to the question,

A worked for (x –3) days, while B worked for x days.

${x - 3}/9 +x/18$ = 1

${2x - 6 + x}/18$ = 1

3x–6 = 18

3x = 18 + 6 = 24 ⇒ x = $24/3$ = 8 days

Using Rule 8,

Here, x = 9, y = 18, m = 3

Total time taken = ${(x + m)y}/{x + y}$

=${(9 + 3) × 18}/{9 + 18}$

= ${12 × 18}/27$ = 8 days

Question : 5

A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in

a) 7 days

b) 11 days

c) 3 days

d) 5 days

Answer: (d)

Work done by B in 9 days = $9/12 = 3/4$ part

Remaining work

= $1 - 3/4 = 1/4$ which is done by A

Time taken by A = $1/4 × 20$ = 5 days

Question : 6

A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ?

a) 24 days

b) 30 days

c) 36 days

d) 18 days

Answer: (d)

(A + B)’s day’s work = $1/30$

(B + C)’s 1 day’s work = $1/24$

(C + A)’s 1 day’s work = $1/20$

2 (A + B + C)’s 1 day’s work = $1/30 + 1/24 + 1/20$

= ${4 + 5 + 6}/120 = = 15/120 = 1/8$

(A + B + C)’s 1 day’s work = $1/16$

(A + B + C)’s 10 days’ work = $10/16 = 5/8$

Remaining work = $1- 5/8 = 3/8$

This part of work is done by A alone.

Now A’s 1 day’s work = $1/16 - 1/24$

= ${3 - 2}/48 = 1/48$

The required no. of days

=$3/8 × 48$ = 18 days

Recently Added Subject & Categories For All Competitive Exams

Most Important Antonyms Vocabulary - IBPS Clerk Prelims 2024

Latest Antonyms multiple choice questions and answers with free PDFfor IBPS Clerk Prelims 2024. English Vocabulary practice exercise for all bank exam

17-May-2024 by Careericons

Continue Reading »

Syllogism Practice Questions Answers PDF - IBPS Clerk 2024

Practice Verbal Reasoning Syllogism multiple choice questions and answers with Fully solved explanation, PDF for the IBPS Clerk Prelims 2024 Bank Exam

16-May-2024 by Careericons

Continue Reading »

IBPS Clerk Prelims 2024 Synonyms Questions Solved Answers

Most important IBPS Clerk Prelims 2024 Synonyms and Antonyms multiple choice questions and answers with detailed solutions, English vocabulary PDF Download

14-May-2024 by Careericons

Continue Reading »

New Cloze Test Questions and Answers PDF - IBPS Clerk 2024

The most important Cloze Test questions with detailed answers for upcoming IBPS Clerk prelims 2024. Latest English verbal ability practice MCQs, PDF

13-May-2024 by Careericons

Continue Reading »