Model 3 Man leaves & joins Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in

(a) 7 days

(b) 11 days

(c) 3 days

(d) 5 days

The correct answers to the above question in:

Answer: (d)

Work done by B in 9 days = $9/12 = 3/4$ part

Remaining work

= $1 - 3/4 = 1/4$ which is done by A

Time taken by A = $1/4 × 20$ = 5 days

Practice time & work (Model 3 Man leaves & joins) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more man leaves and joins Based Quantitative Aptitude Questions and Answers

Question : 1

A and B alone can complete work in 9 days and18 days respectively. They worked together; however 3 days before the completion of the work A left. In how many days was the work completed ?

a) 8 days

b) 6 days

c) 5 days

d) 13 days

Answer: (a)

Let the work be completed in x days.

According to the question,

A worked for (x –3) days, while B worked for x days.

${x - 3}/9 +x/18$ = 1

${2x - 6 + x}/18$ = 1

3x–6 = 18

3x = 18 + 6 = 24 ⇒ x = $24/3$ = 8 days

Using Rule 8,

Here, x = 9, y = 18, m = 3

Total time taken = ${(x + m)y}/{x + y}$

=${(9 + 3) × 18}/{9 + 18}$

= ${12 × 18}/27$ = 8 days

Question : 2

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in :

a) 6 days

b) 10 days

c) 10$1/2$ days

d) 5 days

Answer: (b)

Work done by (B + C) in 3 days.

= $3 × (1/9 + 1/12)$

= $1/3 + 1/4 = {4 + 3}/12 = 7/12$

Remaining work = $1 - 7/12 = 5/12$

This part of work is done by A alone.

Now, $1/24$ part of work is done by A in 1 day.

∴ $5/12$ part of work will be done by A in

= $24 × 5/12$ = 10 days.

Question : 3

A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in

a) 15$2/3$ days

b) 16$1/3$ days

c) 18$2/3$ days

d) 14$1/3$ days

Answer: (d)

A’s 1 day’s work = $1/12$

B’s 1 day’s work = $1/18$

Part of work done by A and B in first two days

= $1/12 + 1/18 = {3 - 2}/36 = 5/36$

Part of work done by A and B in 14 days = $35/36$

[14 days to be taken randomly]

Remaining work = $1 - 35/36 = 1/36$

Now A will work for 15th day.

A will do the $1/36$ work in $1/36 × 12 = 1/3$ day.

Total Work will be done in $14{1}/3$ days.

Question : 4

A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ?

a) 24 days

b) 30 days

c) 36 days

d) 18 days

Answer: (d)

(A + B)’s day’s work = $1/30$

(B + C)’s 1 day’s work = $1/24$

(C + A)’s 1 day’s work = $1/20$

2 (A + B + C)’s 1 day’s work = $1/30 + 1/24 + 1/20$

= ${4 + 5 + 6}/120 = = 15/120 = 1/8$

(A + B + C)’s 1 day’s work = $1/16$

(A + B + C)’s 10 days’ work = $10/16 = 5/8$

Remaining work = $1- 5/8 = 3/8$

This part of work is done by A alone.

Now A’s 1 day’s work = $1/16 - 1/24$

= ${3 - 2}/48 = 1/48$

The required no. of days

=$3/8 × 48$ = 18 days

Question : 5

A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed ?

a) 13 days

b) 12 days

c) 6 days

d) 18 days

Answer: (b)

Work done by 2 (A + B) in one day

= $1/10 + 1/15 = {3 + 2}/30 = 5/30 = 1/6$

Work done by (A + B) in one day = $1/12$

(A + B) can complete the work in 12 days

Question : 6

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in :

a) 8 days

b) 12 days

c) 15 days

d) 10 days

Answer: (b)

Work done by (A + B) in 1 day

= $1/15 + 1/10 = {2 + 3}/30 = 5/30 = 1/6$

(A + B)’s 2 days’ work = $2/6 = 1/3$

Remaining work = $1 - 1/3 = 2/3$

This part is done by A alone.

Since, one work is done by A in 15 days.

$2/3$ work is done in $15 × 2/3$ = 10 days.

Total number of days = 10 + 2 = 12 days

Using Rule 20,

Here, m = 15, n = 10, p =2

A alone completed the work in

= $\text"mn - p(m+n)"/ \text"n"$days

= ${15 × 10 - 2(15 + 10)}/10$

= ${150 - 50}/10$ = 10 days

Total time taken= 10 + 2 = 12 days

Recently Added Subject & Categories For All Competitive Exams

New 100+ Compound Interest MCQ with Answers PDF for IBPS

Compound Interest verbal ability questions and answers solutions with PDF for IBPS RRB PO. Aptitude Objective MCQ Practice Exercises all competitive exams

02-Jul-2024 by Careericons

Continue Reading »

100+ Mixture and Alligation MCQ Questions PDF for IBPS

Most importantly Mixture and Alligation multiple choice questions and answers with PDF for IBPS RRB PO. Aptitude MCQ Practice Exercises all Bank Exams

02-Jul-2024 by Careericons

Continue Reading »

IBPS Profit and Loss Questions Solved Problems with PDF

Most important Profit and Loss multiple choice questions and answers with PDF for IBPS RRB PO. 100+ Aptitude MCQ Practice Exercises all competitive exams

28-Jun-2024 by Careericons

Continue Reading »

100+ Average Aptitude Questions Answers solutions MCQ PDF

New Average multiple choice questions and answers with PDF for IBPS RRB PO. 100+ Quantitative Aptitude MCQ Practice Exercises all competitive exams

28-Jun-2024 by Careericons

Continue Reading »