The following question based on time & work topic of quantitative aptitude

Questions : If A and B together can complete a work in 12 days, B and C together in 15 days and C and A together in 20 days, then B alone can complete the work in

(a) 20 days

(b) 24 days

(c) 30 days

(d) 25 days

The correct answers to the above question in:

Answer: (a)

(A + B)’s 1 day’s work = $1/12$

(B + C)’s 1 day’s work = $1/15$

(C + A)’s 1 day’s work = $1/20$

On adding,

2 (A + B + C)’s 1 day's work = $1/12 + 1/15 + 1/20$

= ${5 + 4 + 3}/60 = 1/5$

(A+B+C)’s 1 day’s work = $1/10$

B’s 1 day’s work = $1/10 - 1/20 = {2 - 1}/20 = 1/20$

B alone can do the work in 20 days.

Using Rule 19,

B alone can do in = ${2 × 12 × 15 × 20}/{-12 × 15 + 15 × 20 + 20 × 12}$

= ${24 × 300}/{-180 + 300 + 240} = {24 × 300}/360$ = 20 days

Practice time & work (Model 1 Basics on Time & Work) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more basics on time and work Based Quantitative Aptitude Questions and Answers

Question : 1

A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?

a) 48 days

b) 40 days

c) 24 days

d) 32 days

Answer: (a)

(A + B)'s 1 day's work = $1/12$ ...(i)

(B + C)'s 1 day's work = $1/8$ ...(ii)

(C + A)'s 1 day's work = $1/6$ ...(iii)

On adding,

2(A + B + C)'s 1 day's work = $1/12 + 1/8 + 1/6$

= ${2 + 3 + 4}/24 = 9/24$

(A+ B + C)'s 1 day’s work = $9/{24 × 2} = 9/48$ ...(iv)

On, subtracting (iii) from (iv),

B’s 1 day’s work = $9/48 - 1/6$

= ${9 - 8}/48 = 1/48$

B can complete the work in 48 days.

Using Rule 19,

B alone can do in = ${2 × 12 × 8 × 6}/{-12 × 8 + 8 × 6 + 6 × 12}$

= ${24 × 48}/{-96 + 48 + 72} = {24 × 48}/{-96 + 120}$

= ${24 × 48}/24$ = 48 days

Question : 2

A and B working together; can do a piece of work in 4$1/2$ hours. B and C working together can do it in 3 hours. C and A working together can do it in 2$1/4$ hours. All of them begin the work at the same time. Find how much time they will take to finish the piece of work.

a) 3·25 hours

b) 2·5 hours

c) 3 hours

d) 2 hours

Answer: (d)

(A + B)’s 1 hour’s work = $2/9$ .....(i)

(B + C)’s 1 hour’s work = $1/3$ ......(ii)

(C + A)’s 1 hour’s work = $4/9$ .....(iii)

Adding all three equations,

2 (A + B + C)’s 1 hour’s work = $2/9 + 1/3 + 4/9$

${2 + 3 + 4}/9$ = 1

A, B and C together will complete the work in 2 hours.

Using Rule 5,

Time taken = ${2 × 9/2 × 3 × 9/4}/{9/2 × 3 + 3 × 9/4 + 9/2 × 9/4}$

= ${{18 × 27}/8}/{27/2 + 27/4 + 81/8}$

= ${18 × 27}/8 × 8/({108 + 54 + 81})$

= ${18 × 27}/243$ = 2 hours

Question : 3

A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :

a) 30 days

b) 80 days

c) 60 days

d) 120 days

Answer: (d)

According to the question

Work done by A and B together in one day = $1/10$ part

Work done by B and C together in one day = $1/15$ part

Work done by C and A together in one day = $1/20$ part

So, A + B = $1/10$ ....(I)

B + C = $1/15$ ...(II)

C + A = $1/20$ ....(III)

Adding I, II, III, we get

2 (A + B + C) = $1/10 + 1/15 + 1/20$

2 (A + B + C) = ${6 + 4 + 3}/60 = 13/60$

A + B + C = $13/120$ ....(IV)

Putting the value of eqn. (I) in eqn. (IV)

$1/10 + C =13/120$

C = $13/120 - 1/10 = {13 - 12}/120 = 1/120$

Work done in 1 day by C is $1/120$ part

Hence, C will finish the whole work in 120 days

Using Rule 19
A and B can do a work in 'x' days, B and C can do the same work in 'y' days. C and A can do the same work in 'z' days. Then, all can do alone the work as following:
A alone can do in =${2xyz}/{xy + yz - zx}$days
B alone can do in =${2xyz}/{-xy + yz + zx}$days
C alone can do in =${2xyz}/{xy - yz + zx}$days

Time Taken by C= ${2xyz}/{xy - yz + zx}$

= ${2 × 10 × 15 × 20}/{10 × 15 - 15 × 20 + 20 × 10 }$

= $6000/{150 - 300 + 200} = 6000/50$ = 120 days

Question : 4

If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work ?

a) 30 days

b) 40 days

c) 60 days

d) 45 days

Answer: (c)

(A + B)’s 1 day’s work = $1/15$

B’s 1 day’s work = $1/20$

A’s 1 day’s work = $1/15 - 1/20 = {4 - 3}/60 = 1/60$

A alone will do the work in 60 days.

Using Rule 4,

A alone do in = ${15 × 20}/{20 - 15}$

= ${15 × 20}/5$ = 60 days

Question : 5

A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?

a) 20 days

b) 16 days

c) 24 days

d) 18 days

Answer: (c)

A’s 1 day’s work = $1/12$

(A+B)’s 1 day’s work = $1/8$

B’s 1 day’s work =$1/8 - 1/12 = {3 - 2}/24 = 1/24$

B alone can do the work in 24 days.

Using Rule 4,

Time taken by B = ${12 × 8}/{12 - 8}$ = 24 days

Recently Added Subject & Categories For All Competitive Exams

SSC STENO 2024: Free Reading Comprehension MCQ Test PDF

Top Reading Comprehension English Section-wise multiple choice questions and answers, Full Mock Test Series & Online Quiz for SSC Steno Grade C & D 2024 Exam

26-Apr-2024 by Careericons

Continue Reading »

Free Percentage Questions Answers for SSC STENO 2024 Exam

Important Top Percentage Aptitude-based multiple choice questions and answers practice quiz series, Online Mock Test PDF for SSC Steno Grade C & D 2024 Exam

25-Apr-2024 by Careericons

Continue Reading »

Free Antonyms (English) MCQ Test for SSC STENO 2024 Exam

Top Antonyms General English Section-based multiple choice questions and answers, Free Full Test Series & Online Quiz PDF for SSC Steno Grade C & D 2024 Exam

24-Apr-2024 by Careericons

Continue Reading »

Free Ratio & Proportion MCQ Test for SSC STENO 2024 Exam

Top Ratio and Proportion Aptitude-based multiple choice questions and answers practice test series, Online MCQ Quiz PDF for SSC Steno (Grade C & D) 2024 Exam

23-Apr-2024 by Careericons

Continue Reading »