Model 5  Split & Fraction of work Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : A does $4/5$ of a piece of work in 20 days; He then calls in B and they finish the remaining work in 3 days. How long B alone will take to do whole work ?

(a) 37 days

(b) $37{1}/2$ days

(c) 23 days

(d) 40 days

The correct answers to the above question in:

Answer: (b)

Using Rule 2,

A can do the whole work in ${20 × 5}/4 = 25$ days

Remaining work = $1 - 4/5 = 1/5$

(A + B)’s 1 day’s work = $1/15$

and A’s 1 day’s work = $1/25$

B’s 1 day’s work

= $1/15 - 1/25 = {5 - 3}/75 = 2/75$

B can finish the work in $75/2$ days

i.e., 37$1/2$ days

Practice time & work (Model 5  Split & Fraction of work) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more split and fraction of work Based Quantitative Aptitude Questions and Answers

Question : 1

A can do $1/2$ of a piece of work in 5 days, B can do $3/5$ of the same work in 9 days and C can do $2/3$ of that work in 8 days. In how many days can three of them together do the work ?

a) 5 days

b) 3 days

c) 4 days

d) 4$1/2$ days

Answer: (c)

Using Rule 3
If A can do a work in 'x' days, B can do the same work in 'y' days, C can do the same work in 'z' days then, total time taken by A, B and C to complete the work together = $1/{1/x + 1/y + 1/z} = {xyz}/{xy + yz + zx}$and
If workers are more than 3 then total time taken by A, B, C ...... so on to complete the work together = $1/{1/x + 1/y + 1/z + ...}$

A can do $1/2$ work in 5 days.

A can do 1 work in 10 days

Similarly,

B can do 1 work in $5/3$ × 9 = 15 days.

C can do 1 work in 8 × $3/2$ = 12 days.

Now, A’s 1 day’s work = $1/10$

B’s 1 day’s work = $1/15$

C’s 1 day’s work = $1/12$

(A + B + C)’s 1 day’s work = $1/10 + 1/15 + 1/12$

= ${6 + 4 + 5}/60 = 15/60 = 1/4$

Hence, (A + B + C) together can complete the work in 4 days.

Question : 2

4 men and 6 women complete a work in 8 days. 2 men and 9 women also complete in 8 days in which. The number of days in which 18 women complete the work is :

a) 5$1/3$ days

b) 4$1/3$ days

c) 5$2/3$ days

d) 4$2/3$ days

Answer: (a)

According to the question,

(4 × 8) men + (6 × 8) women ≡

(2 × 8) men + (9 × 8) women

4 men + 6 women ≡ 2 men + 9 women

(4 - 2) men ≡ (9 - 6) women

2 men ≡ 3 women

4 men + 6 women ≡ 12 women

$M_1D_1 = M_2D_2$

12 × 8 = 18 × $D_2$

$D_2 = {12 × 8}/18 = 16/3 = 5{1}/3$ days

Using Rule 11,

Here, $A_1$ = 4, $B_1$ = 6, $D_1$ = 8

$A_2$ = 2, $B_2$ = 9, $D_2$ = 8

$A_3$ = 0, $B_3$ = 18

Required time = ${D_1D_2(A_1B_2 - A_2B_1)}/{D_1(A_1B_3 - A_3B_1) - D_2(A_2B_3 - A_3 B_2)}$ days

= ${8 × 8(4 × 9 - 2 × 6)}/{8(4 × 18 - 0 × 6) - 8(2 × 18 - 0 × 9)}$

= ${64 × 24}/{8 × 72 - 36 × 8} = 192/36$

= $16/3 = 5{1}/3$ days

Question : 3

A can do in one day three times the work done by B in one day. They together finish $2/5$ of the work in 9 days. The number of days by which B can do the work alone is :

a) 120 days

b) 90 days

c) 30 days

d) 100 days

Answer: (b)

Let time taken by A alone in doing work be x days.

Time taken by B alone = 3x days

A and B together finish $2/5$ work in 9 days.

TIme taken by A and B in doing whole work

= ${9 × 5}/2 = 45/2$ days

$1/x + 1/{3x} = 2/45$

${3 + 1}/{3x} = 2/45$

$4/{3x} = 2/45$ ⇒ 2 × 3x = 4 × 45

$x = {4 × 45}/{2 × 3}$ = 30 days

Time taken by B = 3x days = 3 × 30 = 90 days

Using Rule 22
The efficiency of A to work is 'n' times more than that of B, Both start to work together and finish it in 'D' days. Then, A and B will separately complete, the work in $({n + 1}/n)$D and (n + 1)D days respectively.

Here, n = 3 and D = ${9 × 5}/2 = 45/2$ days

(Time taken to finish whole work)

Time taken by B = (n + 1)D

= (3 + 1) × $45/2$ = 90 days

Question : 4

P can do $(1/4)$th of work in 10 days, Q can do 40% of work in 40 days and R can do $(1/3)$rd of work in 13 days. Who will complete the work first?

a) Q

b) P

c) Both P and R

d) R

Answer: (d)

Since, P does $1/4$ th work in 10 days.

P will do 1 work in 10 × 4 = 40 days

Since, Q, does 40% part of work in 40 days

Q will do 100% work in

${40 × 100}/40$ = 100 days

Since, R, does $1/3$ rd work in 13 days.

R will do 1 work in 13 × 3 = 39 days

Question : 5

A can cultivate $2/5$th of a land in 6 days and B can cultivate $1/3$ rd of the same land in 10 days. Working together A and B can cultivate $4/5$th of the land in:

a) 5 days

b) 4 days

c) 10 days

d) 8 days

Answer: (d)

Using Rule 2,

The part of field cultivated by A in 1 day

= $2/{5 × 6} = 1/15$

The part of field cultivated by B in 1 day

= $1/{3 × 10} = 1/30$

The part of field cultivated by A and B together

= $1/15 + 1/30 = 3/30 = 1/10$

$4/5$ part of field cultivated by A and B together in

= ${4/5}/{1/10}$ days = ${4 × 10}/5 = 8$ days

Question : 6

A and B work together to complete the rest of a job in 7 days. However, $37/100$ of the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

a) 25

b) 20

c) 10

d) 30

Answer: (b)

Remaining work

= $1 - 37/100 = {100 - 37}/100 = 63/100$

Time taken by (A + B) in doing

$63/100$ part of work = 7 days

Time taken by them in doing whole work

= $100/63 × 7 = 100/9$ days

Respective ratio of time taken by

A and B in doing the work = 5 : 4

$1/{4x} + 1/{5x} = 9/100$

${5 + 4}/{20x} = 9/100$

20x = 100 ⇒ x = 5

Required time = 4 × 5 = 20 days

Recently Added Subject & Categories For All Competitive Exams

100+ Quadratic Equation Questions Answers PDF for Bank

Quadratic Equation multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams

03-Jul-2024 by Careericons

Continue Reading »

IBPS Aptitude Linear Equations MCQ Questions Answers PDF

Linear equations multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams

03-Jul-2024 by Careericons

Continue Reading »

New 100+ Compound Interest MCQ with Answers PDF for IBPS

Compound Interest verbal ability questions and answers solutions with PDF for IBPS RRB PO. Aptitude Objective MCQ Practice Exercises all competitive exams

02-Jul-2024 by Careericons

Continue Reading »

100+ Mixture and Alligation MCQ Questions PDF for IBPS

Most importantly Mixture and Alligation multiple choice questions and answers with PDF for IBPS RRB PO. Aptitude MCQ Practice Exercises all Bank Exams

02-Jul-2024 by Careericons

Continue Reading »