Model 5  Split & Fraction of work Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : A and B work together to complete the rest of a job in 7 days. However, $37/100$ of the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

(a) 25

(b) 20

(c) 10

(d) 30

The correct answers to the above question in:

Answer: (b)

Remaining work

= $1 - 37/100 = {100 - 37}/100 = 63/100$

Time taken by (A + B) in doing

$63/100$ part of work = 7 days

Time taken by them in doing whole work

= $100/63 × 7 = 100/9$ days

Respective ratio of time taken by

A and B in doing the work = 5 : 4

$1/{4x} + 1/{5x} = 9/100$

${5 + 4}/{20x} = 9/100$

20x = 100 ⇒ x = 5

Required time = 4 × 5 = 20 days

Practice time & work (Model 5  Split & Fraction of work) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more split and fraction of work Based Quantitative Aptitude Questions and Answers

Question : 1

A can cultivate $2/5$th of a land in 6 days and B can cultivate $1/3$ rd of the same land in 10 days. Working together A and B can cultivate $4/5$th of the land in:

a) 5 days

b) 4 days

c) 10 days

d) 8 days

Answer: (d)

Using Rule 2,

The part of field cultivated by A in 1 day

= $2/{5 × 6} = 1/15$

The part of field cultivated by B in 1 day

= $1/{3 × 10} = 1/30$

The part of field cultivated by A and B together

= $1/15 + 1/30 = 3/30 = 1/10$

$4/5$ part of field cultivated by A and B together in

= ${4/5}/{1/10}$ days = ${4 × 10}/5 = 8$ days

Question : 2

P can do $(1/4)$th of work in 10 days, Q can do 40% of work in 40 days and R can do $(1/3)$rd of work in 13 days. Who will complete the work first?

a) Q

b) P

c) Both P and R

d) R

Answer: (d)

Since, P does $1/4$ th work in 10 days.

P will do 1 work in 10 × 4 = 40 days

Since, Q, does 40% part of work in 40 days

Q will do 100% work in

${40 × 100}/40$ = 100 days

Since, R, does $1/3$ rd work in 13 days.

R will do 1 work in 13 × 3 = 39 days

Question : 3

A does $4/5$ of a piece of work in 20 days; He then calls in B and they finish the remaining work in 3 days. How long B alone will take to do whole work ?

a) 37 days

b) $37{1}/2$ days

c) 23 days

d) 40 days

Answer: (b)

Using Rule 2,

A can do the whole work in ${20 × 5}/4 = 25$ days

Remaining work = $1 - 4/5 = 1/5$

(A + B)’s 1 day’s work = $1/15$

and A’s 1 day’s work = $1/25$

B’s 1 day’s work

= $1/15 - 1/25 = {5 - 3}/75 = 2/75$

B can finish the work in $75/2$ days

i.e., 37$1/2$ days

Question : 4

A can do $7/8$ of work in 28 days, B can do $5/6$ of the same work in 20 days. The number of days they will take to complete if they do it together is

a) 17$3/5$ days

b) 15$3/7$ days

c) 13$5/7$ days

d) 14$5/7$ days

Answer: (c)

Using Rule 2,

A does $7/8$ work in 28 days.

A will complete the work in

$28 × 8/7$ = 32 days.

B does $5/6$ work in 20 days.

B will complete the work in

${20 × 6}/5$ = 24 days

(A + B)’s 1 day’s work

= $1/32 + 1/24 = {3 + 4}/96 = 7/96$

Required time = $96/7 =13{5}/7$ days

Question : 5

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only $5/8$th of the road had been constructed. To complete the work in stipulated time the number of extra labours required is :

a) 10

b) 18

c) 16

d) 12

Answer: (c)

Using Rule 1,

Remaining work

= $1 - 5/8 = 3/8$ ;

Remaining time = 4 days

${M_1D_1}/W_1= {M_2D_2}/W_2$

${20 × 12}/{5/8} = {M_2 × 4}/{3/8}$

${20 × 12}/5 = {M_2 × 4}/3$

4 × 12 = ${M_2 × 4}/3$

$M_2$ = 12 × 3 = 36

Number of additional workers = 36 - 20 = 16

Question : 6

If 28 men complete $7/8$ of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is

a) 6

b) 5

c) 3

d) 4

Answer: (d)

Using Rule1,

WorkDaysMen
$7/8$728
$1/8$7x

$7/8 : 1 8 : : 28 : x$

where x is no. of men

$7/8 × x = 1/8 × 28$

$x = {28 × 8}/{7 × 8}$ = 4

Recently Added Subject & Categories For All Competitive Exams

Syllogism Practice Questions Answers PDF - IBPS Clerk 2024

Practice Verbal Reasoning Syllogism multiple choice questions and answers with Fully solved explanation, PDF for the IBPS Clerk Prelims 2024 Bank Exam

16-May-2024 by Careericons

Continue Reading »

IBPS Clerk Prelims 2024 Synonyms Questions Solved Answers

Most important IBPS Clerk Prelims 2024 Synonyms and Antonyms multiple choice questions and answers with detailed solutions, English vocabulary PDF Download

14-May-2024 by Careericons

Continue Reading »

New Cloze Test Questions and Answers PDF - IBPS Clerk 2024

The most important Cloze Test questions with detailed answers for upcoming IBPS Clerk prelims 2024. Latest English verbal ability practice MCQs, PDF

13-May-2024 by Careericons

Continue Reading »

Mensuration Aptitude Practice Mcq Questions IBPS Clerk 2024

Most Important Practice Mensuration aptitude multiple choice questions, answers with detailed solutions, PDF beginner to advanced for IBPS Clerk Prelims 2024

11-May-2024 by Careericons

Continue Reading »