Model 5  Split & Fraction of work Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : A can finish a work in 18 days and B can do the same work in half the time taken by A. Then working together what part of the same work they can finish in a day ?

(a) $2/5$

(b) $1/6$

(c) $2/7$

(d) $1/9$

The correct answers to the above question in:

Answer: (b)

Using Rule 2,

A’s 1 day’s work = $1/18$

B’s 1 day’s work = $1/9$

(A + B)’s 1 day’s work

= $1/18 + 1/9 = {1 + 2}/18 = 3/18 = 1/6$

Practice time & work (Model 5  Split & Fraction of work) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more split and fraction of work Based Quantitative Aptitude Questions and Answers

Question : 1

A and B can do a piece of work in 72 days, B and C can do it in 120 days, and A and C can do it in 90 days. When A, B and C work together, how much work is finished by them in 3 days.

a) $1/30$

b) $1/40$

c) $1/10$

d) $1/20$

Answer: (d)

Using Rule 5
If A and B can do a work in 'x' days, B and C can do the same work in 'y' days, C and A can do the same work in 'z' days. Then total time taken, when A, B and C
work together =$2/{(1/x + 1/y + 1/z)}$ OR ${2xyz}/{xy + yz + zx}$ days

(A + B)’s 1 day’s work = $1/72$

(B + C)’s 1 day’s work = $1/120$

(C + A)’s 1 day’s work = $1/90$

On adding all three,

2 (A + B + C)’s 1 day’s work

= $1/72 + 1/120 + 1/90 = {5 + 3 + 4}/360 = 1/30$

(A + B + C)’s 1 day’s work = $1/60$

(A + B + C)’s 3 days’ work = $3/60 = 1/20$

Question : 2

P can complete $1/4$ of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes $1/3$ of the work in 13 days and S, $1/6$ of the work in 7 days. Who will be able to complete the work first ?

a) Q

b) P

c) S

d) R

Answer: (a)

Time taken by P in completing 1 work

= 10 × 4 = 40 days

Time taken by Q in completing 1 work

= ${15 × 5}/2 = 75/2$ days

Time taken by R in completing 1 work

= 13 × 3 = 39 days

Time taken by S in completing 1 work

= 7 × 6 = 42 days

Clearly, Q took the least time i.e. $75/2$ or 37${1}/2$ days.

Question : 3

A does half as much work as B in three- fourth of the time. If together they take 18 days to complete a work, how much time shall B take to do it alone?

a) 35 days

b) 30 days

c) 45 days

d) 40 days

Answer: (b)

Using Rule 2,

Let B completes the work in x days.

Work done by A in ${3x}/4$ days = $1/2$

Time taken by A in completing the work = $2 × {3x}/4 = {3x}/2$ days

(A + B)’s 1 day’s work

= $1/x + 2/{3x} = {3 + 2}/{3x} = 5/{3x}$

$5/{3x} = 1/18$ ⇒ 3x = 90 ⇒ x = 30

Hence, time taken by B in completing the work = 30 days

Question : 4

A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in

a) 7$1/2$ days

b) 8 days

c) 6 days

d) 6$1/4$ days

Answer: (a)

A can do a work in 12 days.

B is 60% more efficient than A.

Time taken by B = $(100/160 × 12)$ days

= $15/2 = 7{1}/2$ days

Question : 5

Dhiru can dig $1/a$ of a field in 20 hours. What fraction of the same field can Kaku dig in 20 hours if the two of them can dig the field in 60 hours, working together at their respective rates ?

a) $1/{3a}$

b) ${(a - 3)}/a$

c) ${(a - 3)}/{3a}$

d) ${3a}/{(a - 3)}$

Answer: (c)

Dhiru digs $1/a$ part of field in 20 hours.

Dhiru digs 1 part of field in 20a hours.

= $1/60 - 1/{20a} = {a - 3}/{60a}$

Part of field dug by Kaku in 1 hour

= ${20(a - 3)}/{60a} ={a - 3}/{3a}$

Question : 6

A does half as much work as B in three fourth of the time. If together they take 18 days to complete the work, how much time will B alone take to do it ?

a) 45 days

b) 40 days

c) 30 days

d) 50 days

Answer: (c)

Let the time taken by B in doing the work alone = x days

According to the question,

Time taken by A = $2 × {3x}/4 = {3x}/2$ days

$1/x + 1/{{3x}/2} = 1/18$

$1/x + 2/{3x} = 1/18$

${3 + 2}/{3x} = 1/18$

3x = 18 × 5

$x = {18 × 5}/3$ = 30 days

Recently Added Subject & Categories For All Competitive Exams

Puzzle Reasoning Questions Answers PDF: IBPS Clerk 2024

Top Reasoning Puzzle Test questions with answers, fully solved explanation and download PDF for IBPS Clerk Prelims 2024. Aptitude MCQ-based practice test

20-May-2024 by Careericons

Continue Reading »

Most Important Antonyms Vocabulary - IBPS Clerk Prelims 2024

Latest Antonyms multiple choice questions and answers with free PDFfor IBPS Clerk Prelims 2024. English Vocabulary practice exercise for all bank exam

17-May-2024 by Careericons

Continue Reading »

Syllogism Practice Questions Answers PDF - IBPS Clerk 2024

Practice Verbal Reasoning Syllogism multiple choice questions and answers with Fully solved explanation, PDF for the IBPS Clerk Prelims 2024 Bank Exam

16-May-2024 by Careericons

Continue Reading »

IBPS Clerk Prelims 2024 Synonyms Questions Solved Answers

Most important IBPS Clerk Prelims 2024 Synonyms and Antonyms multiple choice questions and answers with detailed solutions, English vocabulary PDF Download

14-May-2024 by Careericons

Continue Reading »