Model 5 Split & Fraction of work Section-Wise Topic Notes With Detailed Explanation And Example Questions
MOST IMPORTANT quantitative aptitude - 7 EXERCISES
-
Top 199+ Basic Time and Work Aptitude MCQs with Answers »
-
Top 200+ Time and Work Problem Solving By Formula Method »
-
New 189+ Time & Work MCQs Practice Test for BANK Exams »
-
Top 199+ Time & Work MCQs: Men Women Child for BANK Exam »
-
Top 199+ Time and Work Questions Test on Fraction of Work »
-
Top 199+ Time and Work Efficiency Based Aptitude MCQ Quiz »
-
New 299+ Time and Work Aptitude Test On Individual Wages »
The following question based on time & work topic of quantitative aptitude
(a) $2/5$
(b) $1/6$
(c) $2/7$
(d) $1/9$
The correct answers to the above question in:
Answer: (b)
Using Rule 2,
A’s 1 day’s work = $1/18$
B’s 1 day’s work = $1/9$
(A + B)’s 1 day’s work
= $1/18 + 1/9 = {1 + 2}/18 = 3/18 = 1/6$
Discuss Form
Read more split and fraction of work Based Quantitative Aptitude Questions and Answers
Question : 1
A and B can do a piece of work in 72 days, B and C can do it in 120 days, and A and C can do it in 90 days. When A, B and C work together, how much work is finished by them in 3 days.
a) $1/30$
b) $1/40$
c) $1/10$
d) $1/20$
Answer »Answer: (d)
Using Rule 5If A and B can do a work in 'x' days, B and C can do the same work in 'y' days, C and A can do the same work in 'z' days. Then total time taken, when A, B and C work together =$2/{(1/x + 1/y + 1/z)}$ OR ${2xyz}/{xy + yz + zx}$ days
(A + B)’s 1 day’s work = $1/72$
(B + C)’s 1 day’s work = $1/120$
(C + A)’s 1 day’s work = $1/90$
On adding all three,
2 (A + B + C)’s 1 day’s work
= $1/72 + 1/120 + 1/90 = {5 + 3 + 4}/360 = 1/30$
(A + B + C)’s 1 day’s work = $1/60$
(A + B + C)’s 3 days’ work = $3/60 = 1/20$
Question : 2
P can complete $1/4$ of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes $1/3$ of the work in 13 days and S, $1/6$ of the work in 7 days. Who will be able to complete the work first ?
a) Q
b) P
c) S
d) R
Answer »Answer: (a)
Time taken by P in completing 1 work
= 10 × 4 = 40 days
Time taken by Q in completing 1 work
= ${15 × 5}/2 = 75/2$ days
Time taken by R in completing 1 work
= 13 × 3 = 39 days
Time taken by S in completing 1 work
= 7 × 6 = 42 days
Clearly, Q took the least time i.e. $75/2$ or 37${1}/2$ days.
Question : 3
A does half as much work as B in three- fourth of the time. If together they take 18 days to complete a work, how much time shall B take to do it alone?
a) 35 days
b) 30 days
c) 45 days
d) 40 days
Answer »Answer: (b)
Using Rule 2,
Let B completes the work in x days.
Work done by A in ${3x}/4$ days = $1/2$
Time taken by A in completing the work = $2 × {3x}/4 = {3x}/2$ days
(A + B)’s 1 day’s work
= $1/x + 2/{3x} = {3 + 2}/{3x} = 5/{3x}$
$5/{3x} = 1/18$ ⇒ 3x = 90 ⇒ x = 30
Hence, time taken by B in completing the work = 30 days
Question : 4
A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in
a) 7$1/2$ days
b) 8 days
c) 6 days
d) 6$1/4$ days
Answer »Answer: (a)
A can do a work in 12 days.
B is 60% more efficient than A.
Time taken by B = $(100/160 × 12)$ days
= $15/2 = 7{1}/2$ days
Question : 5
Dhiru can dig $1/a$ of a field in 20 hours. What fraction of the same field can Kaku dig in 20 hours if the two of them can dig the field in 60 hours, working together at their respective rates ?
a) $1/{3a}$
b) ${(a - 3)}/a$
c) ${(a - 3)}/{3a}$
d) ${3a}/{(a - 3)}$
Answer »Answer: (c)
Dhiru digs $1/a$ part of field in 20 hours.
Dhiru digs 1 part of field in 20a hours.
= $1/60 - 1/{20a} = {a - 3}/{60a}$
Part of field dug by Kaku in 1 hour
= ${20(a - 3)}/{60a} ={a - 3}/{3a}$
Question : 6
A does half as much work as B in three fourth of the time. If together they take 18 days to complete the work, how much time will B alone take to do it ?
a) 45 days
b) 40 days
c) 30 days
d) 50 days
Answer »Answer: (c)
Let the time taken by B in doing the work alone = x days
According to the question,
Time taken by A = $2 × {3x}/4 = {3x}/2$ days
$1/x + 1/{{3x}/2} = 1/18$
$1/x + 2/{3x} = 1/18$
${3 + 2}/{3x} = 1/18$
3x = 18 × 5
$x = {18 × 5}/3$ = 30 days
time & work Shortcuts and Techniques with Examples
-
Model 1 Basics on Time & Work
Defination & Shortcuts … -
Model 2 Formula method ‘M1D1W1 = M2D2W2’
Defination & Shortcuts … -
Model 3 Man leaves & joins
Defination & Shortcuts … -
Model 4 Working with Man, Woman, Child
Defination & Shortcuts … -
Model 5 Split & Fraction of work
Defination & Shortcuts … -
Model 6 Efficiency of the worker
Defination & Shortcuts … -
Model 7 Working with individual wages
Defination & Shortcuts …
Verbal Reasoning
Question & Answer Quiz
Non Verbal Reasoning
Question & Answer Quiz
Quantitative Aptitude
Question & Answer Quiz
Computer MCQ
Question & Answer Quiz
General English
Question & Answer Quiz
History GK
Question & Answer Quiz
Polity GK
Question & Answer Quiz
Geography GK
Question & Answer Quiz
Economy GK
Question & Answer Quiz
General Awareness GK
Question & Answer Quiz
Recently Added Subject & Categories For All Competitive Exams
100+ Quadratic Equation Questions Answers PDF for Bank
Quadratic Equation multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams
Continue Reading »
IBPS Aptitude Linear Equations MCQ Questions Answers PDF
Linear equations multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams
Continue Reading »
New 100+ Compound Interest MCQ with Answers PDF for IBPS
Compound Interest verbal ability questions and answers solutions with PDF for IBPS RRB PO. Aptitude Objective MCQ Practice Exercises all competitive exams
Continue Reading »
100+ Mixture and Alligation MCQ Questions PDF for IBPS
Most importantly Mixture and Alligation multiple choice questions and answers with PDF for IBPS RRB PO. Aptitude MCQ Practice Exercises all Bank Exams
Continue Reading »