Model 1 Basics on Time & Work Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT quantitative aptitude - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on time & work topic of quantitative aptitude

Questions : A, B and C together can complete a piece of work in 30 minutes. A and B together can complete the same work in 50 minutes. C alone can complete the work in

(a) 150 minutes

(b) 80 minutes

(c) 60 minutes

(d) 75 minutes

The correct answers to the above question in:

Answer: (d)

Work done by (A + B + C) in 1 minute = $1/30$

Work done by (A + B) in 1 minute = $1/50$

Work done by C alone in 1 minute = $1/30 - 1/50$

= ${5 - 3}/150 = 2/150 = 1/75$

C alone will complete the work in 75 minutes.

Using Rule 4,

C alone can do in = ${xy}/{x - y}$

= ${50 × 30}/{50 - 30}$ = 75 minutes

Practice time & work (Model 1 Basics on Time & Work) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more basics on time and work Based Quantitative Aptitude Questions and Answers

Question : 1

A can do a piece of work in 4 hours; B and C can do it in 3 hours. A and C can do it in 2 hours. How long will B alone take to do it ?

a) 24 hours

b) 8 hours

c) 10 hours

d) 12 hours

Answer: (b)

A’s 1 hour’s work = $1/4$

(B + C)’s 1 hour’s work = $1/3$

(A + C)’s 1 hour’s work = $1/2$

C’s 1 hour’s work

= $1/2 - 1/4 = {2 - 1}/4 = 1/4$

and B’s 1 hour’s work

= $1/3 - 1/4 = {4 - 3}/12 = 1/12$

Hence, B alone can do the work in 12 hours.

Question : 2

While working 7 hours a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, working 8 hours a day ?

a) 3.6 days

b) 2.5 days

c) 3 days

d) 4 days

Answer: (c)

A alone can complete the work in 42 days working 1 hour daily. Similarly, B will take 56 days working 1 hour daily.

A 's 1 day's work = $1/42$

B 's 1 day's work = $1/56$

(A + B) 's 1 day's work = $1/42 + 1/56 = {4 + 3}/168 = 7/168$

Time taken by (A + B) working 8 hours daily

= $168/{7 × 8}$ = 3 days

Using Rule 21
If a man can do a certain work in '$d_1$' daysworking '$h_1$' hours in a days, while another man can do the same work in '$d_2$' days working '$h_2$' hours in a day. Whenthey work together everyday 'h' hours, then in how many days work will complete?
Required time = $[{({h_1d_1}) × ({h_2d_2})}/{h_1d_1 + h_2d_2}] 1/h$

Here, $h_1$ = 7 hours, $h_2$ = 7 hours, $d_1$ = 6 days, $d_2$ = 8 days, h = 8 hours

Required Time = $[{({7 × 6}) × ({7 × 8})}/{7 × 6 + 7 × 8}] × 1/8$

= ${42 × 56}/98 × 1/8 = 2352/98 × 1/8 = 24/8$ = 3 days

Question : 3

A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in

a) 7 days

b) 6 days

c) 4 days

d) 5 days

Answer: (b)

(A + B)’s 1 day’s work = $1/8$

(B + C)’s 1 day’s work = $1/12$

(C + A)’s 1 day’s work = $1/8$

On adding,

2 (A + B + C)’s 1 day’s work = $1/8 + 1/12 + 1/8$

${3 + 2 + 3}/24 = 8/24 = 1/3$

(A + B + C)’s 1 day’s work = $1/6$

Hence, the work will be completed in 6 days.

Method 2 :

Time = ${2xyz}/{xy + yz + zx}$

(Here, x = 8, y = 12; z = 8)

= ${2 × 8 × 12 × 8}/{96 + 96 + 64}$

${2 × 8 × 12 × 8}/256$ = 6 days.

Using Rule 5,

Time taken = ${2 × 8 × 12 × 8}/{8 × 12 + 12 × 8 + 8 × 8}$

= ${16 × 96}/{96 + 96 + 64} = {16 × 96}/256$ = 6 days

Question : 4

A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in

a) 8$2/7$ days

b) 5$5/7$ days

c) 28 days

d) 14 days

Answer: (b)

(A + B)’s 1 day’s work = $1/10$

(B + C)’s 1 day’s work = $1/6$

(C + A)’s 1 day’s work = $1/12$

Adding all three

2 (A + B + C)’s 1 day’s work = $1/10 + 1/6 + 1/12$

${6 + 10 + 5}/60 = 21/60 = 7/20$

(A + B + C)’s 1 day’s work = $7/40$

All three together will complete the work in $40/7 = 5{5}/7$ = days

Using Rule 5,

Time taken = ${2 × 10 × 6 × 12}/{10 × 6 + 6 × 12 + 12 × 10}$

= $1440/{60 + 72 + 120}$

= $1440/252 = 40/7 = 5{5}/7$ days

Question : 5

A can do a work in 6 days and B in 9 days. How many days will both take together to complete the work?

a) 3 days

b) 3.6 days

c) 7.5 days

d) 5.4 days

Answer: (b)

According to question,

A can finish the whole work in 6 days.

A’s one day’s work = $1/6$

Similarly, B’s one day’s work = $1/9$

(A + B)’s one day’s work

= $(1/6 + 1/9) = ({3 + 2}/18) = 5/18$

Therefore, (A + B)’s can finish the

whole work in $18/5$ days i.e., 3.6 days.

Using Rule 2
If A completes a piece of work in 'x' days, and B completes the same work in 'y' days, then,
Work done by A in 1 day = $1/x$, Work done by B in 1 day = $1/y$
Work done by A and B in 1 day = $1/x + 1/y = {x + y}/{xy}$
Total time taken to complete the work by A and B both = $({xy}/{x + y})$

Time taken = ${6 × 9}/{9 + 6} = 54/15$ = 3.6 days

Question : 6

A and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work ?

a) 20 days

b) 12 days

c) 8 days

d) 10 days

Answer: (c)

Let A and C complete the work in x days

(A + B)’s 1 day’s work = $1/8$

(B + C)’s 1 day’s work = $1/12$

(C + A)’s 1 day’s work = $1/x$

Then (A + B + B + C + C + A)’s 1 day’s work = $1/8 + 1/12 + 1/x$

2(A + B + C)’s 1 day’s work = ${3x + 2x + 24}/{24x}$

(A + B + C)’s 1 day’s work = ${5x + 24}/{24x × 2}$

According to the question,

(A + B + C)’s 1 day’s work = $1/6$

$1/6 = {5x + 24}/{48x}$

30x + 144 = 48x ⇒ x = $144/18$ = 8 days.

Using Rule 5,

Let the time taken by A and C bc x days

Total time taken = ${2 × 8 × 12 × x}/{8 × 12 + 12 × x + 8 × x}$

6 = ${192x}/{96 +20x}$

576 + 120x = 192x

72x = 576 ⇒ x = 8

Time taken by A and C is 8 days.

Recently Added Subject & Categories For All Competitive Exams

New 100+ Compound Interest MCQ with Answers PDF for IBPS

Compound Interest verbal ability questions and answers solutions with PDF for IBPS RRB PO. Aptitude Objective MCQ Practice Exercises all competitive exams

02-Jul-2024 by Careericons

Continue Reading »

100+ Mixture and Alligation MCQ Questions PDF for IBPS

Most importantly Mixture and Alligation multiple choice questions and answers with PDF for IBPS RRB PO. Aptitude MCQ Practice Exercises all Bank Exams

02-Jul-2024 by Careericons

Continue Reading »

IBPS Profit and Loss Questions Solved Problems with PDF

Most important Profit and Loss multiple choice questions and answers with PDF for IBPS RRB PO. 100+ Aptitude MCQ Practice Exercises all competitive exams

28-Jun-2024 by Careericons

Continue Reading »

100+ Average Aptitude Questions Answers solutions MCQ PDF

New Average multiple choice questions and answers with PDF for IBPS RRB PO. 100+ Quantitative Aptitude MCQ Practice Exercises all competitive exams

28-Jun-2024 by Careericons

Continue Reading »