Model 1 Basics on Time & Work Practice Questions Answers Test with Solutions & More Shortcuts
time & work PRACTICE TEST [7 - EXERCISES]
Model 1 Basics on Time & Work
Model 2 Formula method ‘M1D1W1 = M2D2W2’
Model 3 Man leaves & joins
Model 4 Working with Man, Woman, Child
Model 5 Split & Fraction of work
Model 6 Efficiency of the worker
Model 7 Working with individual wages
Question : 26 [SSC Constable (GD) 2012]
A, B and C individually can do a work in 10 days, 12 days and 15 days respectively. If they start working together, then the number of days required to finish the work is
a) 2 days
b) 4 days
c) 16 days
d) 8 days
Answer »Answer: (b)
Work done by A, B and C in 1 day
= $1/10 + 1/12 + 1/15 = {6 + 5 + 4}/60$
= $15/60 = 1/4$
Required time = 4 days
Using Rule 3,
Time Taken = ${xyz}/{xy + yz + zx}$
= ${10 × 12 × 15}/{10 × 12 + 12 × 15 + 15 × 10}$
= $1800/{120 + 180 + 150}$
= $1800/450$ = 4 days
Question : 27 [SSC GL Tier-I 2013]
A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
a) 15$2/3$ days
b) 10 days
c) 5 days
d) 7$5/6$ days
Answer »Answer: (b)
According to question,
A and B can do a work in 12 days
(A + B)'s one day's work = $1/12$
Similarly, (B + C)'s one day's work = $1/15$
and (C + A)'s one day's work = $1/20$
On adding all three,
2 (A + B + C)'s one days's work
= $1/12 + 1/15 + 1/20 = {10 + 8 + 6}/120 = 1/5$
(A + B + C)'s one days's work = $1/10$
A, B and C together can finish the whole work in 10 days.
Using Rule 5If A and B can do a work in 'x' days, B and C can do the same work in 'y' days, C and A can do the same work in 'z' days. Then total time taken, when A, B and C work together =$2/{(1/x + 1/y + 1/z)}$ OR ${2xyz}/{xy + yz + zx}$ days
Time taken = ${2 × 12 × 15 × 20}/{12 × 15 + 15 × 20 + 20 × 12}$
= ${24 × 300}/{180 + 300 + 240} = 7200/720$ = 10 days.
Question : 28 [SSC GL Tier-I 2013]
A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work?
a) 60 days
b) 30 days
c) 10 days
d) 20 days
Answer »Answer: (b)
(P + Q)’s 1 day’s work = $1/12$ ...(i)
(Q + R)’s 1 day’s work = $1/15$ ...(ii)
(R + P)’s 1 day’s work = $1/20$ ...(iii)
Adding all three equations,
2 (P + Q + R)’s 1 day’s work = $1/12 + 1/15 + 1/20$
${5 + 4 + 3}/60 = 12/60 = 1/5$
(P + Q + R)’s 1 day’s work = $1/10$ ...(iv)
P’s 1 day’s work = $1/10 - 1/15 = {3 - 2}/30 = 1/30$
P alone will complete the work in 30 days.
Question : 29 [SSC CGL Prelim 2000]
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?
a) 18 days
b) 9 days
c) 4 days
d) 6 days
Answer »Answer: (c)
According to question,
10 men’s one day’s work = $1/12$
1 man one day’s work =$1/{12 × 10} = 1/120$
Similarly, 1 woman one day’s work = $1/{6 × 10} = 1/60$
(1 man + 1 woman)’s one day’s work = $1/120 + 1/60$
= ${1 + 2}/120 = 3/120 = 1/40$
(10 men + 10 women)’s one day’s work = $10/40 = 1/4$
Therefore, both the teams can finish the whole work in 4 days.
Question : 30 [SSC CPO S.I.2009]
A and B can do a piece of work in 10 days. B and C can do it in 12 days. C and A in 15 days. In how many days will C finish it alone ?
a) 60 days
b) 40 days
c) 24 days
d) 30 days
Answer »Answer: (b)
(A + B)'s 1 day's work = $1/10$ ... (i)
(B + C)'s 1 day’s work = $1/12$ ... (ii)
(C + A)’s 1 day’s work = $1/15$ ... (iii)
On adding all these,
2(A + B + C)’s 1 day’s work = $1/10 + 1/12 + 1/15$
= ${6 + 5 + 4}/60 = 1/4$
(A + B + C)’s 1 day’s work = $1/8$ … (iv)
C’s 1 day’s work = $1/8 - 1/10 = {5 - 4}/40 = 1/40$
C will finish the work in 40 days.
Using Rule 19,
C alone can do in = ${2 × 10 × 12 × 15}/{10 × 12 - 12 × 15 + 10 × 15}$
= ${240 × 15}/{120 - 180 + 150} = {240 × 15}/90$ = 40 days
IMPORTANT quantitative aptitude EXERCISES
-
Top 199+ Basic Time and Work Aptitude MCQs with Answers »
-
Top 200+ Time and Work Problem Solving By Formula Method »
-
New 189+ Time & Work MCQs Practice Test for BANK Exams »
-
Top 199+ Time & Work MCQs: Men Women Child for BANK Exam »
-
Top 199+ Time and Work Questions Test on Fraction of Work »
-
Top 199+ Time and Work Efficiency Based Aptitude MCQ Quiz »
-
New 299+ Time and Work Aptitude Test On Individual Wages »
Model 1 Basics on Time & Work Shortcuts »
Click to Read...Model 1 Basics on Time & Work Online Quiz
Click to Start..time & work Shortcuts and Techniques with Examples
-
Model 1 Basics on Time & Work
Defination & Shortcuts … -
Model 2 Formula method ‘M1D1W1 = M2D2W2’
Defination & Shortcuts … -
Model 3 Man leaves & joins
Defination & Shortcuts … -
Model 4 Working with Man, Woman, Child
Defination & Shortcuts … -
Model 5 Split & Fraction of work
Defination & Shortcuts … -
Model 6 Efficiency of the worker
Defination & Shortcuts … -
Model 7 Working with individual wages
Defination & Shortcuts …
quantitative aptitude CATEGORIES
RECENT BLOGS
Recently Added Subject & Categories For All Competitive Exams
Free Percentage Questions Answers for SSC STENO 2024 Exam
Important Top Percentage Aptitude-based multiple choice questions and answers practice quiz series, Online Mock Test PDF for SSC Steno Grade C & D 2024 Exam
Continue Reading »
Free Antonyms (English) MCQ Test for SSC STENO 2024 Exam
Top Antonyms General English Section-based multiple choice questions and answers, Free Full Test Series & Online Quiz PDF for SSC Steno Grade C & D 2024 Exam
Continue Reading »
Free Ratio & Proportion MCQ Test for SSC STENO 2024 Exam
Top Ratio and Proportion Aptitude-based multiple choice questions and answers practice test series, Online MCQ Quiz PDF for SSC Steno (Grade C & D) 2024 Exam
Continue Reading »
Free Synonyms (English) MCQ Test for SSC STENO 2024 Exam
Top Synonyms General English Section-based multiple choice questions and answers, Free Full Test Series & Online Quiz PDF for SSC Steno Grade C & D 2024 Exam
Continue Reading »