Question :16

A man, a woman or a boy can do a job in 20 days, 30 days or 60 days respectively. How many boys must assist 2 men and 8 women to do the work in 2 days ?

Answer: (c)

Man's two day's work = $2 × 1/{20}$ th work $1/{10}$ th work

Woman's two days's work

= 2 × $1/{30}$ th work = $1/{15}$ th work

Boy's two day's work = 2 × $1/{60}$ th work = $1/{30}$ th work

Now, let 2 men, 8 women and x boys can complete work in 2 days. Then ,

2 men's work +8 women's work + x boy's work =1

$2(1/{10}) + 8(1/{15}) + x(1/{30}) = 1$

⇒ x = $(1 - 1/5 - 8/{15}) × 30$⇒ x = 8 boys

Question :17

A person has to cover a distance of 6 km in 45 minutes. If he covers one-half of the distance in two-thirds of the total time; to cover the remaining distance in the remaining time, his speed (in km/h) must be:

Answer: (b)

Remaining distance = 3 km

and remaining time = $(1/3 × 45)min = 15 min = 1/4$ hr.

∴ Required speed = (3 × 4) km/h = 12 km/hr.

Question :18

If 6 men can do a piece of work in 30 days of 9 hours each, how many men will it take to do 10 times the amount of work if they work 25 days of 8 hours each ?

Answer: (a)

Number of man = ${30×6×9}/{25×8}$×10

= 81 men

Question :19

A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time ?

Answer: (a)

50 men complete 0.4 work in 25 days.

Applying the work rule, $m_1 × d_1 × w_2 = m_2 × d_2 × w_1$

we have,

50 × 25 × 0.6 = $m_2$ × 25 × 0.4

or $m_2 = {50 × 25 × l 0.6}/{25 × 0.4}$ = 75 men

Number of additional men required = (75 – 50) = 25

Question :20

A can do a piece of work in 10 days, while B alone can do it in 15 days. They work together for 5 days and the rest of the work is done by C in 2 days. If they get Rs 450 for the whole work, how should they divide the money ?

Answer: (a)

Work done by A and B in 5 days = $(1/{10} + 1/{15}) × 5 = 5/6$

Work remaining = $1 - 5/6 = 1/6$

∴ C alone can do the work in 6 × 2 = 12 days

Ratio of their share work = $5/{10} : 5/{15} : 2/{12} = 3 : 2 : 1$

Share of wages = Rs 225, Rs 150, Rs 75.

ssc chsl tier 1 2023 IMPORTANT QUESTION AND ANSWERS

Recently Added Subject & Categories For All Competitive Exams

100+ Quadratic Equation Questions Answers PDF for Bank

Quadratic Equation multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams

03-Jul-2024 by Careericons

Continue Reading »

IBPS Aptitude Linear Equations MCQ Questions Answers PDF

Linear equations multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams

03-Jul-2024 by Careericons

Continue Reading »

New 100+ Compound Interest MCQ with Answers PDF for IBPS

Compound Interest verbal ability questions and answers solutions with PDF for IBPS RRB PO. Aptitude Objective MCQ Practice Exercises all competitive exams

02-Jul-2024 by Careericons

Continue Reading »

100+ Mixture and Alligation MCQ Questions PDF for IBPS

Most importantly Mixture and Alligation multiple choice questions and answers with PDF for IBPS RRB PO. Aptitude MCQ Practice Exercises all Bank Exams

02-Jul-2024 by Careericons

Continue Reading »