time and work mcq pdf Model Questions & Answers, Practice Test for ibps rrb so officer sclae 2 3 single exam 2024

Question :1

Seven men can complete a work in 12 days. They started the work and after 5 days, two men left. In how many days will the work be completed by the remaining men?

Answer: (e)

(7 × 12) men can complete the work in 1 day.

∴ 1 man's 1 day's work = $1/{84}$.

7 men's 5 days' work = $(1/12 × 5) = 5/{12}$.

Remaining work = $(1-{5/12}) = 7/12$.

5 men's 1 day's work = $(1/84 × 5) = 5/{84}$.

$5/{84}$ work is done by them in 1 day.

$7/{12}$ work is done by them in

$({84}/5 × 7/{12}) = {{49}/5} days = 9{4/5}$ days

Question :2

If a family of 9 men in Indore spends Rs.16380 in a year, what must be the expenses of 8 men in Calcutta who live in the same style for 7 months, assuming that the prices at Calcutta are 3/5th of what they are in Indore ?

Answer: (a)

The factors by which the expenses change are = 8/9 × 7/12 × 3/5 × 16380 = 5096 for 7 months.

Question :3

If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be

Answer: (c)

Given (6 M + 8 B) ×10=(26 M + 48 B)×2

⇒60M+80B=52M+96B

⇒8M=16B

⇒1M=2B

∴15M+20B=30B+20B=50B

6M+8B=12B+8B=20B

Now

BoysDays
2010
50 ↓x (Let)

∴ X = ${20 ×10}/{50}$ = 4days

Question :4

76 ladies complete a job in 33 days. Due to some reason some ladies did not join the work and therefore, it was completed in 44 days. The number of ladies who did not report for the work is

Answer: (a)

Here $M_1 D_1 = M_2 D_2$

$M_1 = 76 Ladies, M_2$ = x Let

$D_1 = 33 days D_2$ = 44 days

⇒76 × 33 = x × 44

∴ x = 57 days

no. of ladies who did not Report

for work = 76 – 57 = 19.

Question :5

Two men and 7 children complete a certain piece of work in 4 days, while 4 men and 4 children complete the same work in only 3 days. The number of days required by 1 man to complete the work is :

Answer: (c)

(2M + 7C)'s 1 day's work = $1/4$

⇒ work will be completed by 4 (2M + 7C) = 8 M + 28 C

Again, (4M + 4C)'s 1 day's work = $1/3$

i.e. 12M + 12C will complete the work.

⇒8M + 28C = 12M + 12C or M = 4C

Therefore, 4M + 4C = 5M

Since 5M complete a work in 3 days,

1 M will complete it in 15 days.

ibps rrb so officer sclae 2 3 single exam 2024 IMPORTANT QUESTION AND ANSWERS

Recently Added Subject & Categories For All Competitive Exams

100+ Quadratic Equation Questions Answers PDF for Bank

Quadratic Equation multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams

03-Jul-2024 by Careericons

Continue Reading »

IBPS Aptitude Linear Equations MCQ Questions Answers PDF

Linear equations multiple choice questions with detailed answers for IBPS RRB SO. more than 250 Attitude practice test exercises for all competitive exams

03-Jul-2024 by Careericons

Continue Reading »

New 100+ Compound Interest MCQ with Answers PDF for IBPS

Compound Interest verbal ability questions and answers solutions with PDF for IBPS RRB PO. Aptitude Objective MCQ Practice Exercises all competitive exams

02-Jul-2024 by Careericons

Continue Reading »

100+ Mixture and Alligation MCQ Questions PDF for IBPS

Most importantly Mixture and Alligation multiple choice questions and answers with PDF for IBPS RRB PO. Aptitude MCQ Practice Exercises all Bank Exams

02-Jul-2024 by Careericons

Continue Reading »