Practice Working with individual wages - quantitative aptitude Online Quiz (set-1) For All Competitive Exams

Q-1)   7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

(a)

(b)

(c)

(d)

Explanation:

WorkDaysMen
1127
28x

∴ ${1 : 2}/{8 : 12}]$ : : 7 : x

where, x is no. of men

1 × 8 × x = 2 × 12 × 7

$x = {7 × 12 × 2}/8 = 21$

Number of additional men = 21 - 7 = 14

Metod 2 : Using Rule 1,

$M_1D_1W_2 = M_2D_2W_1$

7 × 12 × 2 = $M_2$ × 8 × 1

$M_2 = {7 × 12 × 2}/8 = 21$

No. of additional men = 21 - 7 = 14


Q-2)   Two persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?

(a)

(b)

(c)

(d)

Explanation:

WorkDaysPersons
192
212x

where x = number of persons

∴ ${1 : 2}/{12 : 9}]$ : : 2 : x

1×12 × x = 2 × 9 × 2

$x = {2 × 9 × 2}/12$ = 3

Using Rule 1,

Here, $M_1 = 2, W_1 = 1, D_1$ = 9

$M_2 = ?, W_2 = 2, D_2$ = 12

$M_1D_1W_2 = M_2D_2W_1$

2 × 9 × 2 = $M_2$ × 12 × 1

$M_2 = 36/12$ = 3


Q-3)   24 men can do a piece of work in 17 days. How many men will be able to do it in 51 days ?

(a)

(b)

(c)

(d)

Explanation:

$M_1D_1 = M_2D_2$

24 × 17 = $M_2$ × 51

$M_2 = {24 × 17}/51$ = 8 men


Q-4)   If the work done by (x –1) men in (x + 1) days is to the work done by (x + 2) men in (x - 1) days are in the ratio 9 : 10, then the value of x is equal to :

(a)

(b)

(c)

(d)

Explanation:

Using Rule 1,

${M_1D_1}/W_1 = {M_2D_2}/W_2$

$W_1/W_2 = {M_1D_1}/{M_2D_2}$

$9/10 = {(x - 1)(x + 1)}/{(x + 2)(x - 1)} = {x + 1}/{x + 2}$

10x + 10 = 9x + 18

x = 18 - 10 = 8


Q-5)   If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m?

(a)

(b)

(c)

(d)

Explanation:

Using Rule 1,

We know that

$W_1/{M_1D_1} = W_2/{M_2D_2}$

$280/{72 × 21} = 100/{x × 18}$

Where x = number of men

x × 18 × 280 = 100 × 72 × 21

$x = {100 × 72 × 21}/{18 × 280}$ = 30


Q-6)   ‘x’ number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is

(a)

(b)

(c)

(d)

Explanation:

MenDays
x30
x + 620

x + 6 : x : : 30 : 20

${x + 6}/x = 30/20 = 3/2$

2x + 12 = 3x

3x - 2x = 12 ⇒ x = 12

Using Rule 1,

Here, $M_1 = x, D_1 = 30, M_2 = x + 6, D_2$ = 20

$M_1D_1 = M_2D_2$

x × 30 = (x + 6) × 20

$3x = 2x + 12$ ⇒ x = 12


Q-7)   Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

(a)

(b)

(c)

(d)

Explanation:

Using Rule 1,

Let the original number of carpenters be x.

$M_1D_1 = M_2D_2$

x × 9 = (x - 5) × 12

9x = 12x - 60

3x = 60 ⇒ x = 20


Q-8)   4 mat-weavers can weave 4 mats in 4 days. At the same rate how many mats would be woven by 8 mat-weavers in 8 days ?

(a)

(b)

(c)

(d)

Explanation:

Using Rule 1,

WeaverDaysMats
444
88x

∴ ${4 : 8}/{4 : 8}]$ : : 4 : x

where, x is no. of mats

4 × 4 × x = 8 × 8 × 4

$x = {8 × 8 × 4}/{4 × 4}$ = 16


Q-9)   A wall of 100 metres can be built by 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres ?

(a)

(b)

(c)

(d)

Explanation:

Using Rule 1,

7 men ≡ 10 women

or 1 man = $10/7$ women

14 men + 20 women

= $({10 × 14}/7 + 20)$ women = 40 women

Now, more work, more days

More women, less days

∴ ${Work - {1 : 6}}/{Women - {40 : 10}}]$ : : 10 : x

Where x = number of days

1 × 40 × x = 6 × 10 × 10

or $x = 600/40$ = 15


Q-10)   A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is :

(a)

(b)

(c)

(d)

Explanation:

Using Rule 1,

200 men do $1/4$ work in 50 days.

${M_1D_1}/W_1 = {M_2D_2}/W_2$

${200 × 50}/{1/4} = {M_2 × 100}/{3/4}$

$M_2 × 100 = 200 × 50 × 3$

$M_2$ = 300

Additional men = 100