Model 1 Basics On Time & Work Section-Wise Topic Notes With Detailed Explanation And Example Questions

MOST IMPORTANT QUANTITATIVE APTITUDE - 7 EXERCISES

Top 10,000+ Aptitude Memory Based Exercises

The following question based on Time & Work topic of Quantitative Aptitude

Questions : A and B working together; can do a piece of work in 4$1/2$ hours. B and C working together can do it in 3 hours. C and A working together can do it in 2$1/4$ hours. All of them begin the work at the same time. Find how much time they will take to finish the piece of work.

(a) 3·25 hours

(b) 2·5 hours

(c) 3 hours

(d) 2 hours

The correct answers to the above question in:

Answer: (d)

(A + B)’s 1 hour’s work = $2/9$ .....(i)

(B + C)’s 1 hour’s work = $1/3$ ......(ii)

(C + A)’s 1 hour’s work = $4/9$ .....(iii)

Adding all three equations,

2 (A + B + C)’s 1 hour’s work = $2/9 + 1/3 + 4/9$

${2 + 3 + 4}/9$ = 1

A, B and C together will complete the work in 2 hours.

Using Rule 5,

Time taken = ${2 × 9/2 × 3 × 9/4}/{9/2 × 3 + 3 × 9/4 + 9/2 × 9/4}$

= ${{18 × 27}/8}/{27/2 + 27/4 + 81/8}$

= ${18 × 27}/8 × 8/({108 + 54 + 81})$

= ${18 × 27}/243$ = 2 hours

Practice Time & Work (Model 1 Basics On Time & Work) Online Quiz

Discuss Form

Valid first name is required.
Please enter a valid email address.
Your genuine comment will be useful for all users! Each and every comment will be uploaded to the question after approval.

Read more basics on time and work Based Quantitative Aptitude Questions and Answers

Question : 1

A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :

a) 30 days

b) 80 days

c) 60 days

d) 120 days

Answer: (d)

According to the question

Work done by A and B together in one day = $1/10$ part

Work done by B and C together in one day = $1/15$ part

Work done by C and A together in one day = $1/20$ part

So, A + B = $1/10$ ....(I)

B + C = $1/15$ ...(II)

C + A = $1/20$ ....(III)

Adding I, II, III, we get

2 (A + B + C) = $1/10 + 1/15 + 1/20$

2 (A + B + C) = ${6 + 4 + 3}/60 = 13/60$

A + B + C = $13/120$ ....(IV)

Putting the value of eqn. (I) in eqn. (IV)

$1/10 + C =13/120$

C = $13/120 - 1/10 = {13 - 12}/120 = 1/120$

Work done in 1 day by C is $1/120$ part

Hence, C will finish the whole work in 120 days

Using Rule 19
A and B can do a work in 'x' days, B and C can do the same work in 'y' days. C and A can do the same work in 'z' days. Then, all can do alone the work as following:
A alone can do in =${2xyz}/{xy + yz - zx}$days
B alone can do in =${2xyz}/{-xy + yz + zx}$days
C alone can do in =${2xyz}/{xy - yz + zx}$days

Time Taken by C= ${2xyz}/{xy - yz + zx}$

= ${2 × 10 × 15 × 20}/{10 × 15 - 15 × 20 + 20 × 10 }$

= $6000/{150 - 300 + 200} = 6000/50$ = 120 days

Question : 2

A and B together can complete a piece of work in 18 days, B and C in 24 days and A and C in 36 days. In how many days, will all of them together complete the work ?

a) 10 days

b) 12 days

c) 16 days

d) 15 days

Answer: (c)

(A + B)’s 1 day’s work = $1/18$

(B + C)’s 1 day’s work = $1/24$

(A + C)’s 1 day’s work = $1/36$

Adding all three,

2 (A + B + C)’s 1 day’s work= $1/18 + 1/24 + 1/36$

= ${4 + 3 + 2}/72 = 1/8$

(A + B + C)’ 1 day’s work = $1/16$

A, B and C together will complete the work in 16 days.

Using Rule 5,

Total time taken = ${2 × 18 × 24 × 36}/{18 × 24 +24 × 36 + 36 × 18}$

= ${36 × 24 × 36}/{432 + 864 + 648}$

= $31104/1944$ = 16 days

Question : 3

A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :

a) 4$4/9$ days

b) 5$5/47$ days

c) 3$3/4$ days

d) 3$3/7$ days

Answer: (b)

(A + B)'s 1 day's work = $1/8$ ...(i)

(B + C)'s 1 day's work = $1/6$ ...(ii)

(C + A)'s 1 day's work = $1/10$ ...(iii)

On adding,

2(A + B + C)'s 1 day's work = $1/8 + 1/6 + 1/10$

= ${15 + 20 + 12}/120 = 47/120$

(A + B + C)'s 1 day’s work= $47/240$

(A + B + C) together will complete the work in

$240/47 = 5{5}/47$ days.

Using Rule 5,

Time taken = ${2 × 8 × 6 × 10}/{8 × 6 + 6 × 10 + 10 × 8}$

= $960/{48 + 60 + 80} = 960/188$

= $240/47 = 5{5}/47$ days

Question : 4

A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?

a) 48 days

b) 40 days

c) 24 days

d) 32 days

Answer: (a)

(A + B)'s 1 day's work = $1/12$ ...(i)

(B + C)'s 1 day's work = $1/8$ ...(ii)

(C + A)'s 1 day's work = $1/6$ ...(iii)

On adding,

2(A + B + C)'s 1 day's work = $1/12 + 1/8 + 1/6$

= ${2 + 3 + 4}/24 = 9/24$

(A+ B + C)'s 1 day’s work = $9/{24 × 2} = 9/48$ ...(iv)

On, subtracting (iii) from (iv),

B’s 1 day’s work = $9/48 - 1/6$

= ${9 - 8}/48 = 1/48$

B can complete the work in 48 days.

Using Rule 19,

B alone can do in = ${2 × 12 × 8 × 6}/{-12 × 8 + 8 × 6 + 6 × 12}$

= ${24 × 48}/{-96 + 48 + 72} = {24 × 48}/{-96 + 120}$

= ${24 × 48}/24$ = 48 days

Question : 5

If A and B together can complete a work in 12 days, B and C together in 15 days and C and A together in 20 days, then B alone can complete the work in

a) 20 days

b) 24 days

c) 30 days

d) 25 days

Answer: (a)

(A + B)’s 1 day’s work = $1/12$

(B + C)’s 1 day’s work = $1/15$

(C + A)’s 1 day’s work = $1/20$

On adding,

2 (A + B + C)’s 1 day's work = $1/12 + 1/15 + 1/20$

= ${5 + 4 + 3}/60 = 1/5$

(A+B+C)’s 1 day’s work = $1/10$

B’s 1 day’s work = $1/10 - 1/20 = {2 - 1}/20 = 1/20$

B alone can do the work in 20 days.

Using Rule 19,

B alone can do in = ${2 × 12 × 15 × 20}/{-12 × 15 + 15 × 20 + 20 × 12}$

= ${24 × 300}/{-180 + 300 + 240} = {24 × 300}/360$ = 20 days

Question : 6

If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work ?

a) 30 days

b) 40 days

c) 60 days

d) 45 days

Answer: (c)

(A + B)’s 1 day’s work = $1/15$

B’s 1 day’s work = $1/20$

A’s 1 day’s work = $1/15 - 1/20 = {4 - 3}/60 = 1/60$

A alone will do the work in 60 days.

Using Rule 4,

A alone do in = ${15 × 20}/{20 - 15}$

= ${15 × 20}/5$ = 60 days

Recently Added Subject & Categories For All Competitive Exams

IBPS PO MAINS 2025: Sentence Improvement Questions PDF

Get Free PDF of Sentence Improvement English Questions Answer with practice Mock Test and explore various examples for IBPS PO MAINS 2025, Bank, Govt Exams

07-Feb-2025 by Careericons

Continue Reading »

IBPS PO MAINS 2025: One Word Substitution Mock Test, PDF

Get Free PDF of One Word Substitution English Questions Answer with practice Mock Test and explore various examples for IBPS PO MAINS 2025, Bank, Govt Exams

05-Feb-2025 by Careericons

Continue Reading »

100+ Para Jumbles Mock Test, PDF for IBPS PO MAINS 2025

Get a Free PDF of Para Jumbles General English Questions Answer with practice Mock Test and explore various examples for IBPS PO MAINS 2025, Bank, Govt Exams

04-Feb-2025 by Careericons

Continue Reading »

Coded Inequality Mock Test, PDF for IBPS PO MAINS 2025

Get a Free PDF of Coded Inequality Reasoning Questions Answer with practice Mock Test and explore various examples for IBPS PO MAINS 2025, Bank, Govt Exams

31-Jan-2025 by Careericons

Continue Reading »